Experiment Schedule



Table 5: Experiment Schedule
From To Hall-A Status E99-117 Time (days)
06/01/01 06/02/01 1.198 GeV/15$\mu A$/pol Commission 2
06/03/01 06/05/01 5.734 GeV/15$\mu A$/pol x=0.61 $\perp$ 3
06/06/01 06/18/01 5.734 GeV/15$\mu A$/pol x=0.61 $\parallel$ 14
06/19/01 06/19/01 5.734 GeV/15$\mu A$/pol x=0.33 $\parallel$ $e^+$ 0.2
(06/19/01) (06/19/01) 5.734 GeV/15$\mu A$/pol (x=0.48 $\parallel$ $e^+$) (0.2)
06/19/01 06/20/01 5.734 GeV/15$\mu A$/pol x=0.33 $\perp$ 0.8+0.3$\star$
06/20/01 06/24/01 5.734 GeV/15$\mu A$/pol x=0.33 $\parallel$ 4.6+0.3
06/25/01 06/30/01 5.734 GeV/15$\mu A$/pol x=0.48 $\parallel$ 5.1+0.2
06/30/01 07/01/01 5.734 GeV/15$\mu A$/pol x=0.48 $\perp$ 1.2+0.2
07/02/01 07/08/01 Holiday   5
07/09/01 07/12/01 Maintenance target tests 4
07/13/01 07/14/01 5.734 GeV/15$\mu A$/pol x=0.61 $\perp$ 1.5
07/14/01 07/19/01 5.734 GeV/15$\mu A$/pol x=0.61 $\parallel$ 5.5

$\star$ there is one extra day added due to hall schedule change and is unevenly distributed between two lower $x$ kinematics such that better statistic error can be achieved at lowest $x$ point, where $A_1^n$ is expected to be small.