Commissioning

Beam energy 1.198 GeV, 15 $\mu A$, $\theta_L=\theta_R=20^\circ$, $p_L=p_R=p$ .



Table 6: E99-117 Commissioning
Date Task Target $I_{beam}$
($\mu A$)
$p$(GeV/c) Time Note
  Beam Tuning     (1.1903) $\sim$16 through Compton Chicane
06/01 OTR       0.5  
  Compton Set-up       $\sim$8 check beam profile
  BPM/Harp BeO     1 Det checking start
  Charge asym       1$\sim$2  
  Moller $^{12}$C     3 using optics target
  Mott ?     0.5  
  ep $^{12}$C     1  
  ARC $^{12}$C     1 Det checking end
  Optics $^{12}$C 25 el, 1.1903 0.1 raster on, open collimator
  Optics $^{12}$C 5 el, 1.1903 0.1 raster off, sieve slits in
  Optics $^{12}$C 5 QE, 1.112 0.1 raster off, sieve slits in
  False asym $^{12}$C 25 QE, 1.112 1.0 raster on, open collimator
06/02 Elastic $\vec{^3\rm {He}}_\parallel$ 15 el, 1.168 13.3 check asym, $\sigma$, raster on, open collimator
  Delta resonance $\vec{^3\rm {He}}_\perp$ 5 $\Delta$, 0.796 0.5 check transverse asym sign, raster on, open collimator
  Reference cell r.N$_2$ 15 el,1.1914 0.5 pressure curve, $f$, raster on, open collimator
    r.N$_2$ 15 el,1.1914 0.4 check false asym, raster on, open collimator
    r.$^4$He 15 el, 1.175 0.1 for normalization, raster on, open collimator
    r.$^3$He 15 el, 1.168 1.0 pressure curve, (norm.), raster on, open collimator
    r.$^3$He 15 QE, 1.112 0.4 check false asym, raster on, open collimator

Pressure curve for reference cells should be measured at 4 points with 2.5, 5.0, 7.5 and 10.0 atm, respectively.

Cross sections are measured to the level of 1%, $^3$He elasitic asymmetry is measured to the level of 3%, reference cell $^3$He false asymmetry is measured to $2\times 10^{-4}$.

For $^{12}$C elastic run, at $20^\circ$ the rate will be about 250 Hz at 5$\mu A$, the HRS momentum should be shifted higher (from 1.1903 to 1.200) to reduce the contribution from QE peak within the acceptance.

Compton measurement will be continuously running during the experiment.