Updated August 1
To Pull Out A Stack
- cut AC power
- remove x-terminal platforms
- double check VDC clearances on both arms
- shut off gas
- remove VDC
- disconnect
- gas
- HV
- LV
- TDC cables
- fan power cables
- Ground strap to box beam
- Lifting beams at front and rear of VDC
- undo bolt at stops
- mate transfer frame
- pull VDC out
- lift to floor
- install stops at end of flat wheel track - drill and tap for 1/2" grade 8 bolts
- disconnect cables at rear of stack
- disconnect telephone, AC and PSS cables
- install exit window covers
- pull stack out
- Electron stack (first)
- remove gas cherenkov
- remove Total Absorber
- configure rigging ( adjust slings )
- lift to floor
- metal spacers under grooved wheels
- Hadron stack (second)
- remove Aerogel
- lift to floor
- metal spacers under grooved wheels
Three Weeks On The Floor
- work on FPP gas leaks ????
- cut/install mounting plates for flex tray (to clear bayonet box)
- install VESDA in huts
To Put The Right Arm Stack Back In (first)
- lift up from floor
- install gas cherenkov
- connect telephone, AC and PSS cables
- connect cables at rear of stack
- pull stack back in hut
- install VDC
To Put The Left Arm Stack Back In (second)
- lift up from floor
- install reflection aerogel
- install gas cherenkov
- connect telephone, AC and PSS cables
- connect cables at rear of stack
- pull stack back in hut
- install VDC
Sometime During the Down
- Delay spools
- JLG to center of arms
- small JLG to service platform for VESDA and delay patch cables
- install mounts for 128 spools on right arm
- install studs on right arm
- 85 from left to right, 43 new spools
- 5 per "C" bracket
- 17 old brackets from left, 9 new brackets
- 20 brackets on the inside, 6 more on the outside
- install with aerial lift (JLG)
- install 4 extra patch panels on right arm
- 3 on the inside
- 1 more on the outside
- install 105' patch cables on right arm
- stow away old, unused patch cables on left arm
- Signal lines
- extra ethernet to electron (done)
- (2 of ?????) BPM VME crate lines to electron (status???)
- Gas lines to gas shed
- gas line to left hut (done)
- gas return line to left hut (done - connect at pivot)
- gas status cable to left hut (status???)