Updated September 13
To Put The Right Arm Stack Back In (first)
- lift up from floor
- install gas cherenkov
- connect telephone, AC and PSS cables
- connect cables at rear of stack
- pull stack back in hut
- install VDC
To Put The Left Arm Stack Back In (second)
- lift up from floor
- install reflection aerogel
- install gas cherenkov
- connect telephone, AC and PSS cables
- connect cables at rear of stack
- pull stack back in hut
- install VDC
Sometime During the Down
- Delay spools
- add 112 spools on right arm
- 50 from left to right, 62 new spools
- 5 per "C" bracket
- 10 old brackets from left, 12 new brackets
- 20 brackets on the inside, 2 more on the outside, 2 spools under boxbeam
- install with cantilever and JLG
- shove 24 105' patch cables from left to right side of right hut
- stow away old, unused patch cables on left arm
- Signal lines
- extra ethernet to electron (done)
- (2 of ?????) BPM VME crate lines to electron (status???)
- Gas lines to gas shed
- gas line to left hut (done)
- gas return line to left hut (done - connect at pivot)
- gas status cable to left hut (status???)