How Do I Rig This HRS Detector?



Rail Extensions for Mounting/Removing Detectors

Contents list for the toolboxes on the Detector Service Platforms

Removal of Detector Stack from the Shielding Hut

Installation of Detector Stack into the Shielding Hut

Notes on Electron Arm Detector Stack Removal From Shielding House
when stack was on right arm

Measured tension, when pulling out with small electric winch, as 600 to 700 lbs. 600 lbs initially.
Measured 1050 lbs when frame crossed bump where the removable section of angle meets the fixed section of angle.
Reset dial indicator and at end of pull it showed 850 lbs tension for maximum.
Frame was static with 300 to 400 lbs of tension on the wire.

Electron Detector Stack

Hadron Detector Stack

Equipment List

Vertical Drift Chambers

Measured weight of flipping stand and one VDC: 741 lbs.
Measured weight of one VDC and double wide unistrut support frames for flipping stand: 613 lbs.
Measured weight of transfer frame, VDCs and cables: 3,100 lbs.
Measured weight of transfer frame: 1700 lbs.
There are 4 fixed lifting holes on the Transfer Frame. A 1 inch shackle should be used on each lift hole. Sufficient size to prevent pinching of the sling at the lifting hole. Use two 24 foot slings. Attach the slings from right side to left side of the Transfer Frame. This allows tilting of the frame. Bring the centers of the slings up to the crane hook. The slings should be long enough to not load the aluminum cover of the VDCs. 24 foot is empirically determined. At leat one jack ( 10" Simplex bottle jack ) will be required at the rear (towards the target) of the transfer frame. The jacks are used to support the transfer frame, so we can remove the crane. U-channel stops should be in place on the Transfer Frame on the end which doesn't mate to the fixed frame. They prevent VDCs from sliding off the Transfer Frame. The crane should be used to bring the rails of the transfer frame in line with the rails of the fixed frame. Seat the rails a little way on. Jack up the rear of the Transfer Frame to support it. Remove sling closest to shielding house. Move crane back and support end of frame with jack by the crane. Remove jack. Adjust height of end of Transfer Frame and seat rails fully. Install jack under crane supported end of Transfer Frame. Disconnect slings from the Transfer Frame and move crane out of the way. Place a tie-down around the closest beams of the two frames at the mating ends, to prevent the frames from bing pulled apart. When pulling the VDC out on its sliding bearings there is sufficient friction to pull the transfer frame off the fixed frame and bottle jack support. This would be a bad thing. Slide VDCs out onto the Transfer Frame. Remove tie-down holding the two frames together. At this point only the friction of the bearings prevent the VDCs from sliding off when Transfer Frame is pulled away from the fixed frame. Reattach the slings and lift with crane until crane is supporting a good portion of the load. Use a jack to force the Transfer Frame to disconnect from the fixed frame. Using a jack should help prevent the crane from lifting up or shifting the fixed frame. When free, set on service platform. Attach U-channel stops to mating end of the Transfer Frame.

Scintillator Planes

Gas Cerenkov

Carbon Blocks

Straw Tube Wire Chambers

Detector Space Frame Assemblies

Delay Spool Assemblies

Portable Staircase for Detector stack

Detector Support Platform (from Hall B surplus)

Detector Support Platform (from ODU surplus)

Lead Glass Array for Hadron Arm ( Pion Rejector ) ( Second Version )

Aerogel Diffusion Box - A1

Aerogel Diffusion Box - A2

Big Bite

When In Doubt, Throw It Out


sin(a-b) = sin(a)cos(b) - cos(a)sin(b)
v**2 = 2*g*r*(1-sin(alpha))
r*cos(alpha)*m*g = F*h 
Back to Jack's Notes