Difference between revisions of "G2p Target Minutes"
Line 8: | Line 8: | ||
On Phone: J.Maxwell | On Phone: J.Maxwell | ||
− | * | + | *JP Chen: |
− | 1) Reminded everyone to go through each sub- | + | 1) Reminded everyone to go through each sub-system and see if we are missing any potential issues due the target height offset (by 9cm).<br> |
− | 2) | + | 2) Stressed on the importance of knowing the target field very well and mentioned about doing a field measurement in the target lab. <br> |
+ | 3) J. Zhang agreed to volunteer in setting up a simple device to measure field at few different places and cross-check with the existing map.<br> | ||
+ | 4) Ed mentioned that there is translation table in Hall A (originally from Hall-C) which was used earlier to do the same thing, and can be used again.<br> | ||
+ | 5) Mentioned about getting a short write-up ready by 28th April for the review committee. | ||
+ | |||
+ | |||
+ | *C. Keith: | ||
+ | 1) The magnet is shipped to JLab and currently somewhere in the US.<br> | ||
+ | 2) All electronics for the 2.5T field have not been located yet(?)<br> | ||
+ | 3) Duke EIO is better and will minimize the swap time between 5T and 2.5T electronics. <br> | ||
+ | 4) finished modifications to the gas panel, wiring for the magnet and waiting for the valves.<br> | ||
+ | 5) Refrigerator design is 99.9% finished.<br> | ||
+ | 6) James is looking into the lifting mechanism | ||
+ | 7) Other small items are ordered (thermometer etc..) | ||
+ | |||
+ | * Al Gavalya: | ||
+ | 1) Mentioned about the items bought/machined by collaborators (Rutgers, Israel group etc..) <br> | ||
+ | 2) There is 8 week delay for Tungsten <br> | ||
+ | 3) Al will updated run list containing sequence in which the runs at different settings are planned for all the energies. JP and Tim will provide the necessary plan. |
Revision as of 18:32, 21 April 2011
For the target meetings before 04/07/2011 see here
Minutes of the weekly analysis meetings
4/21/2011:
Attendees: C.Keith, Ed folts, K.Allada, J.Zhang, JP.Chen, Al Gavalya, T.Michalski
On Phone: J.Maxwell
- JP Chen:
1) Reminded everyone to go through each sub-system and see if we are missing any potential issues due the target height offset (by 9cm).
2) Stressed on the importance of knowing the target field very well and mentioned about doing a field measurement in the target lab.
3) J. Zhang agreed to volunteer in setting up a simple device to measure field at few different places and cross-check with the existing map.
4) Ed mentioned that there is translation table in Hall A (originally from Hall-C) which was used earlier to do the same thing, and can be used again.
5) Mentioned about getting a short write-up ready by 28th April for the review committee.
- C. Keith:
1) The magnet is shipped to JLab and currently somewhere in the US.
2) All electronics for the 2.5T field have not been located yet(?)
3) Duke EIO is better and will minimize the swap time between 5T and 2.5T electronics.
4) finished modifications to the gas panel, wiring for the magnet and waiting for the valves.
5) Refrigerator design is 99.9% finished.
6) James is looking into the lifting mechanism
7) Other small items are ordered (thermometer etc..)
- Al Gavalya:
1) Mentioned about the items bought/machined by collaborators (Rutgers, Israel group etc..)
2) There is 8 week delay for Tungsten
3) Al will updated run list containing sequence in which the runs at different settings are planned for all the energies. JP and Tim will provide the necessary plan.