Difference between revisions of "Feb runplan"
Line 2: | Line 2: | ||
− | == Straight-through Beamline Commissioning (Y. Roblin) == | + | == Straight-through Beamline Commissioning (Y. Roblin) 29 Feb - Mar 1st == |
Initial Beam Accelerator Ops, with assistance from the Hall A shift crew. This includes delivery of beam to the dump, commissioning of the BPMs, calibration with the Harp and power up of the rasters. | Initial Beam Accelerator Ops, with assistance from the Hall A shift crew. This includes delivery of beam to the dump, commissioning of the BPMs, calibration with the Harp and power up of the rasters. | ||
Line 24: | Line 24: | ||
# Check BPM, slow and fast raster signals in the data | # Check BPM, slow and fast raster signals in the data | ||
# Is spot++ working for both arms? | # Is spot++ working for both arms? | ||
− | # HARP scan | + | # Do HARP scan |
− | # BPM | + | # BPM calibration by Pengjia [http://hallaweb.jlab.org/experiment/g2p/collaborators/kalyan/Beam_Position_Reconstruction_for_g2p.pdf here] |
## It includes calibrating beam positions with both straight-thru and target field ON | ## It includes calibrating beam positions with both straight-thru and target field ON | ||
# Check BCM signals in the scalers (HRS, third arm) | # Check BCM signals in the scalers (HRS, third arm) | ||
Line 78: | Line 78: | ||
# Establish non linearity of the Lumi detectors | # Establish non linearity of the Lumi detectors | ||
# Measure lumi asymmetries | # Measure lumi asymmetries | ||
+ | |||
+ | == Straight-through Optics (Mar 2nd- Mar 4th)== | ||
+ | (Resp : Jixie, Min et al.) | ||
+ | |||
+ | # Cycle magnets? | ||
+ | # Use carbon target and set HRS to elastic setting. | ||
+ | # Septum field vs current, checks with carbon elastic peaks | ||
+ | ## Set the dipole first and then tune quads? | ||
== On-line Analysis == | == On-line Analysis == | ||
Line 92: | Line 100: | ||
# Start-of-Run and End-of-Run information is up to date with all relevant info | # Start-of-Run and End-of-Run information is up to date with all relevant info | ||
− | == Compton Test (2 shifts) == | + | == Compton Test (2 shifts, Mar 3-4) == |
(Resp: Sirish et al.) | (Resp: Sirish et al.) | ||
Line 99: | Line 107: | ||
# ?? | # ?? | ||
− | == Commissioning Beamline Chicane == | + | == Moller Commissioning (1 shift, Mar. 3- 4) == |
+ | |||
+ | (Resp: O. Glamazdin, J. Zhang) | ||
+ | |||
+ | # Detector HV tuning (30min) | ||
+ | # Q1 and Q2 quadruple magnets scan (1hour) | ||
+ | # Moller target longitudinal scan (30 min) | ||
+ | # Beam polarization measurement (30-40min) | ||
+ | # MCC job (to set Moller settings and to restore previous beam parameters) (~2hours) | ||
+ | Total: 5 hours. | ||
+ | |||
+ | == Commissioning Beamline Chicane (March 5th onwards)== | ||
# Mostly Y. Roblin will be driving this part (I will put an ATLis link when it is available): | # Mostly Y. Roblin will be driving this part (I will put an ATLis link when it is available): | ||
Line 110: | Line 129: | ||
# Move to GEp production | # Move to GEp production | ||
− | == Optics | + | == Optics with chicane (March 5th onwards) == |
(Resp: Jixie, Min, Vince et al.) | (Resp: Jixie, Min, Vince et al.) | ||
<U> HRS and Septum Magnet Checks</U> | <U> HRS and Septum Magnet Checks</U> | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
#With beam going through chicane: | #With beam going through chicane: | ||
## Full details are provided at : [http://hallaweb.jlab.org/experiment/g2p/collaborators/jixie/20120226_Optics_Final/g2p_optics_plan.pdf Optics run plan] | ## Full details are provided at : [http://hallaweb.jlab.org/experiment/g2p/collaborators/jixie/20120226_Optics_Final/g2p_optics_plan.pdf Optics run plan] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
== Polarized Target == | == Polarized Target == |
Revision as of 15:19, 28 February 2012
E08-027/E08-007 Commissioning Runplan (K. Slifer / K. Allada)
Contents
- 1 Straight-through Beamline Commissioning (Y. Roblin) 29 Feb - Mar 1st
- 2 HRS/Detector Checkout
- 3 Straight-through Optics (Mar 2nd- Mar 4th)
- 4 On-line Analysis
- 5 Compton Test (2 shifts, Mar 3-4)
- 6 Moller Commissioning (1 shift, Mar. 3- 4)
- 7 Commissioning Beamline Chicane (March 5th onwards)
- 8 Optics with chicane (March 5th onwards)
- 9 Polarized Target
- 10 Beam Energy Measurement
Straight-through Beamline Commissioning (Y. Roblin) 29 Feb - Mar 1st
Initial Beam Accelerator Ops, with assistance from the Hall A shift crew. This includes delivery of beam to the dump, commissioning of the BPMs, calibration with the Harp and power up of the rasters.
Full Details for ONLY straight-through beam delivery are provided at:
Start-up configuration
- Two pass beam, E0 =2.2 GeV, polarized, no raster.
- Current: Initially pulsed up to 2-4<math>\mu</math>A pulsed, then up to 5 <math>\mu</math>A CW.
- Spectrometers at 12.5 degrees, <math>P_0=??</math> MeV (carbon elastic).
- Sieve slits : OUT.
- Septa settings: 5.69 degrees.
- Compton chicane: OFF.
- Polarized Target chicane : OFF and degaussed.
- Tungsten Calorimeter : Retracted.
- Polarized Target: Field OFF
Beam Diagnostics Check-out (Pengjia, Alexandre, Kalyan)
- Check BPM, slow and fast raster signals in the data
- Is spot++ working for both arms?
- Do HARP scan
- BPM calibration by Pengjia here
- It includes calibrating beam positions with both straight-thru and target field ON
- Check BCM signals in the scalers (HRS, third arm)
Tungsten Calorimeter Check-out (Alexandre, Pengjia)
(Can be done either in straight-through or when going through Chicane)
- Commission tungsten calorimeter
- BCM calibration ?
- How do we establish that we can achieve ~1% measurement ?
HRS/Detector Checkout
(Resp: g2p students)
- Most of these check-out can be done during the initial beamline commissioning( both straight-through or when going through Chicane).
- The order in which these checks are done do not matter (some of them are independent).
- After we finish these checks we should be ready to do optics runs with target field.
HRS Detectors Check-out (Melissa, Ryan, Vince)
- Check all the detectors in both arm to establish that we don't have problems.
- Post ALL the online plots for the detectors (ADC, TDC etc..) in the Halog
- VDC (efficiencies etc..)
- Gas Cerenkov (ADC and timing peaks)
- S1 and S2m (ADC and timing peaks)
- Lead-glass Calorimeter (ADC)
- Check HV on all the detectors, align the peaks if necessary
DAQ/Trigger Check-out (Melissa, Ryan, Vince)
- Establish the DAQ conditions for production
- What is the max rate DAQ can run with < 20% DT (Buffered and unbuffered mode) ?
- Record deadtime as a function of DAQ rate. Change rate via current or prescalers.
- Check synchronization of ROCs in buffered mode
- Make sure all important scaler channels are working (BCM, Helicity, triggers, L1A, clock)
- Check scalers in S1 and S2m detectors for double pulsing
Third Arm Detector Check-out (Chao, Kalyan)
- Set thresholds for 2.2 GeV beam
- Check for bad channels, double peaks etc ..
- Check deadtime, helicity, BCM scalers
Helicity Checks (Chao, Pengjia, Kalyan)
- Larger charge asymmetry runs to check BCM/helicity signals in HAPPEX, HRS, thirdarm, Moller DAQs simultaneously
- Establish that there are no problems by checking Hall-A beam charge asymmetries measured in Hall-C
Lumi Detector Check-out (Pengjia, Kalyan)
- Adjust HV with 100nA current to make sure all channels are roughly aligned and there is no saturation in Happex ADC
- Establish non linearity of the Lumi detectors
- Measure lumi asymmetries
Straight-through Optics (Mar 2nd- Mar 4th)
(Resp : Jixie, Min et al.)
- Cycle magnets?
- Use carbon target and set HRS to elastic setting.
- Septum field vs current, checks with carbon elastic peaks
- Set the dipole first and then tune quads?
On-line Analysis
(Resp: Toby)
- Make sure all on-line analysis scripts are up to date on both arms
- Post easy instructions for the shift crew on how to start online analysis (stick notes near the DAQ machine)
- Make sure all the important information is recorded correctly in the datastream:
- EPICS: Beam diagnostics(BCM, BPM, HARP etc..)
- Target variables
- Helicity sorted scalers information ( triggers, L1A, BCM, helicity etc.)
- Helicity in ADC, scaler, TIR
- Start-of-Run and End-of-Run information is up to date with all relevant info
Compton Test (2 shifts, Mar 3-4)
(Resp: Sirish et al.)
- Establish beam through Compton chicane
- ??
Moller Commissioning (1 shift, Mar. 3- 4)
(Resp: O. Glamazdin, J. Zhang)
- Detector HV tuning (30min)
- Q1 and Q2 quadruple magnets scan (1hour)
- Moller target longitudinal scan (30 min)
- Beam polarization measurement (30-40min)
- MCC job (to set Moller settings and to restore previous beam parameters) (~2hours)
Total: 5 hours.
Commissioning Beamline Chicane (March 5th onwards)
- Mostly Y. Roblin will be driving this part (I will put an ATLis link when it is available):
- Start with E0 = 2.2 GeV , B = 2.5 Tesla and theta_target = 90 deg
- Check beam diagnostics again, when going through chicane
- We can do some of our optics while Yves is doing this checks (Jixie et al.)
- BPM+slow raster calibration can also be done during this time (Pengjia)
- E0= 2.2 GeV, B = 5 Tesla and theta_target = 6 deg
- Continue doing optics (Jixie et al.)
- Move to GEp production
Optics with chicane (March 5th onwards)
(Resp: Jixie, Min, Vince et al.)
HRS and Septum Magnet Checks
- With beam going through chicane:
- Full details are provided at : Optics run plan
Polarized Target
(Resp : Target group)
- ??
Beam Energy Measurement
(Resp: Doug?)
- Mott ?