(New page: Go back to Daily Run Plan Daily Run Plans * General considerations ** Nickie Hirlinger Saylor is the current Run Coordinator. Please contact directly via RC phone 757-876-1787 ** Follo...) |
|||
(2 intermediate revisions by the same user not shown) | |||
Line 7: | Line 7: | ||
** The target operator is required to supervise the cryo-target. | ** The target operator is required to supervise the cryo-target. | ||
** Make sure to use the <b>DVCS CODA configuration</b> for all runs (<b>even when taking single arm HRS data</b>). | ** Make sure to use the <b>DVCS CODA configuration</b> for all runs (<b>even when taking single arm HRS data</b>). | ||
− | |||
Line 13: | Line 12: | ||
** Wait for beam, then call RC. | ** Wait for beam, then call RC. | ||
** Prepare to do beam line run plan: | ** Prepare to do beam line run plan: | ||
+ | ** [https://hallaweb.jlab.org/wiki/index.php/Beamline Beamline run plan.] | ||
*** BeO | *** BeO | ||
*** Carbon Hole | *** Carbon Hole | ||
*** Bullseye Scan / Harp (bpm pedestal) | *** Bullseye Scan / Harp (bpm pedestal) |
Latest revision as of 06:09, 6 March 2015
Go back to Daily Run Plan Daily Run Plans
- General considerations
- Nickie Hirlinger Saylor is the current Run Coordinator. Please contact directly via RC phone 757-876-1787
- Follow the generic Instructions for shift takers
- Shift leaders: Please make sure to fill out the beam time accounting form and write a "Shift Summary" log entry at the end of your shift regardless if there is beam or not.
- In general, Hall technical staff should not be contacted by the shift crew - please call the RC first.
- The target operator is required to supervise the cryo-target.
- Make sure to use the DVCS CODA configuration for all runs (even when taking single arm HRS data).
- Instructions for this shift
- Wait for beam, then call RC.
- Prepare to do beam line run plan:
- Beamline run plan.
- BeO
- Carbon Hole
- Bullseye Scan / Harp (bpm pedestal)