Difference between revisions of "Commissioning Run Plan 2016"

From Hall A Wiki
Jump to: navigation, search
(New page: For the Spring of 2016 assume: <ul> <li>Maximum beam current = 20-25 μA but for short times it can go higher for boiling studies and BCM calibration. <li>2.3 GeV @ 1st pass, 4.48 GeV @...)
 
Line 2: Line 2:
 
<ul>
 
<ul>
 
<li>Maximum beam current = 20-25 &mu;A but for short times it can go higher for boiling studies and BCM calibration.
 
<li>Maximum beam current = 20-25 &mu;A but for short times it can go higher for boiling studies and BCM calibration.
<li>2.3 GeV @ 1st pass, 4.48 GeV @ 2nd Pass, 8.84 GeV @ 4th pass, and 11.02 GeV @ 5th pass. No third pass beam in the Spring of 2016.
+
<li>2.3 GeV @ 1st pass, 4.48 GeV @ 2nd Pass, 8.84 GeV @ 4th pass, and 11.02 GeV @ 5th pass.  
 +
<li> <b>No third pass beam in the Spring of 2016</b>.
 
<li> Angle restrictions with DVCS calorimeter in place:
 
<li> Angle restrictions with DVCS calorimeter in place:
 
<ol>
 
<ol>

Revision as of 13:57, 31 January 2016

For the Spring of 2016 assume:

  • Maximum beam current = 20-25 μA but for short times it can go higher for boiling studies and BCM calibration.
  • 2.3 GeV @ 1st pass, 4.48 GeV @ 2nd Pass, 8.84 GeV @ 4th pass, and 11.02 GeV @ 5th pass.
  • No third pass beam in the Spring of 2016.
  • Angle restrictions with DVCS calorimeter in place:
    1. HRS-BL: 17.9 to 45 degrees
    2. HRS-BR: 48.74 to 74.5 degrees