* <b>2nd Pass (E<SUB>beam</SUB> = 4.5 GeV)</b> Time estimate: 12 hours<br>
+
* <b>2nd Pass (E<SUB>beam</SUB> = 4.5 GeV)</b> Time estimate: 7 hours<br>
  
 
<table border="1"  style="width:80%">
 
<table border="1"  style="width:80%">

Revision as of 19:03, 15 February 2016

Proton Elastic Kinematics

* If you need to increase the spectrometer momentum setting, make sure you cycle Q2 and Q3 as per the cycling procedure.
* Elastic electron rates assume 20 μA on 15 cm LH2 target, 5 mSr acceptance.
* Use the following prescale factors: ps1=1, ps2=1, ps3=1, ps8=100. All other triggers should have zero prescale factor. 
* A GMp expert will check the data quality.
  • 2nd Pass (Ebeam = 4.5 GeV) Time estimate: 12 hours
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA hours at 20 μA
15 cm LH2 2 x 2 mm2 4.481 1.547 52.91 5.5 1.4 7 (for 35k events)
15 cm Dummy 2 x 2 mm2 4.481 1.547 52.91 5.5 0.26 4 (for 3.7k events)


  • 4th Pass (Ebeam = 8.8 GeV) Time estimate: 22 days
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA days at 20 μA
15 cm LH2 2 x 2 mm2 8.841 2.101 48.74 12.65 0.018 21 (for 32k events)
15 cm Dummy 2 x 2 mm2 8.841 2.101 48.74 12.65 ----


  • 5th Pass (Ebeam = 11.0 GeV) Time estimate: 39 days
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA days at 20 μA
15 cm LH2 2 x 2 mm2 11.021 2.204 48.74 16.54 0.003 38 (for 10k events)
15 cm Dummy 2 x 2 mm2 11.021 2.204 48.74 16.54 ----


  • 2nd Pass (Ebeam = 4.5 GeV) Time estimate: 7 hours
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA hours at 20 μA
15 cm LH2 2 x 2 mm2 4.481 1.706 48.75 5.2 2.4 4 (for 35k events)
15 cm Dummy 2 x 2 mm2 4.481 1.706 48.75 5.2 0.4 2.5 (for 3.6k events)