Difference between revisions of "Preparations-DOE2016-Nov-Review"

From Hall A Wiki
Jump to: navigation, search
(DOE 2015 review ( Nov 7 and 8th ))
(DOE 2015 review ( Nov 7 and 8th ))
Line 12: Line 12:
 
**[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2016/05/report_on_ecal_prototype_test-ver3.pdf Report] on the thermal annealing test of prototype calorimeter.
 
**[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2016/05/report_on_ecal_prototype_test-ver3.pdf Report] on the thermal annealing test of prototype calorimeter.
 
**[https://hallaweb.jlab.org/wiki/index.php/SBS_DOE_Monthly_Reports Monthly reports]
 
**[https://hallaweb.jlab.org/wiki/index.php/SBS_DOE_Monthly_Reports Monthly reports]
**Recommendations tracker
+
**[https://hallaweb.jlab.org/wiki/images/5/51/Response_to_DOE_2015_November_SBS_Review.pdf Recommendations tracker document]
 
**Conceptual design report for the polarize 3He target
 
**Conceptual design report for the polarize 3He target
 +
**Report on trigger and DAQ

Revision as of 16:45, 20 July 2016

Response to DOE 2015 review report

  1. report from DOE Nov 2015 SBS review.
  2. DOE Nov 2015 recommendations with responses. Initial response to the recommendations and comments.

DOE 2015 review ( Nov 7 and 8th )

  • Agenda.
  • Initial Drafts due by October 3rd for posting to wiki and overview by collaboration.
  • Dry run talks sometime between Oct 17-28th. Talk are due to Review committee by Nov 3rd.
  • Background Material (provide to Review committee by Oct 24th)