Difference between revisions of "Preparations-DOE2016-Nov-Review"
From Hall A Wiki
(→DOE 2016 review ( Nov 7 and 8th )) |
|||
Line 8: | Line 8: | ||
===DOE 2016 review ( Nov 7 and 8th ) === | ===DOE 2016 review ( Nov 7 and 8th ) === | ||
+ | * [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2016/08/sbs_site_charge_letter_2016_final.pdf Charge letter] for review. | ||
+ | *[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2016/08/sbs_2016_review_panel_list.pdf Panel List] for review. | ||
* Agenda. | * Agenda. | ||
* Initial Drafts due by October 3rd for posting to wiki and overview by collaboration. | * Initial Drafts due by October 3rd for posting to wiki and overview by collaboration. |
Revision as of 12:35, 1 August 2016
Response to DOE 2015 review report
- Cover letter for DOE Nov 2015 SBS review.
- Excerpts from DOE Nov 2015 SBS review.
- report from DOE Nov 2015 SBS review.
- DOE Nov 2015 recommendations with responses. Initial response to the recommendations and comments.
DOE 2016 review ( Nov 7 and 8th )
- Charge letter for review.
- Panel List for review.
- Agenda.
- Initial Drafts due by October 3rd for posting to wiki and overview by collaboration.
- Dry run talks sometime between Oct 17-28th. Talk are due to Review committee by Nov 3rd.
- Background Material (provide to Review committee by Oct 24th)
- PMP
- Report on the thermal annealing test of prototype calorimeter.
- Monthly reports
- Recommendations tracker document
- Conceptual design report for the polarize 3He target
- Report on trigger and DAQ