Difference between revisions of "PREX/CREX Readiness"

From Hall A Wiki
Jump to: navigation, search
Line 18: Line 18:
 
| Target ladder installation || Simona Malace || Incomplete || - || - || -
 
| Target ladder installation || Simona Malace || Incomplete || - || - || -
 
|-
 
|-
| Target motion test || Bill Henry || Incomplete || - || Measured precision/repeatability || -
+
| Target motion test || Bill Henry || Incomplete || will do at time of survey|| Measured precision/repeatability || -
 
|-
 
|-
 
| Magnet cooldown test || Simona Malace || Incomplete || - || - || -
 
| Magnet cooldown test || Simona Malace || Incomplete || - || - || -
Line 24: Line 24:
 
!colspan="6" style="text-align:left;"| Documentation/Expertise Development (Oversight: Simona Malace)
 
!colspan="6" style="text-align:left;"| Documentation/Expertise Development (Oversight: Simona Malace)
 
|-
 
|-
| How to take a run || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
+
| How to take a run || Bill Henry/ Cameron Clarke || Incomplete || November|| - || -
 
|-
 
|-
| How to analyze a run || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
+
| How to analyze a run || Bill Henry/ Cameron Clarke || Incomplete || November || - || -
 
|-
 
|-
 
| How to determine dead time || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
 
| How to determine dead time || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
 
|-
 
|-
| How to adjust thresholds || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
+
| How to adjust thresholds || Bill Henry/ Cameron Clarke || Incomplete || Start Dec. 2 || - || -
 
|-
 
|-
| How to determine/adjust quad/dip current || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
+
| How to determine/adjust quad/dip current || Bill Henry/ Cameron Clarke || Incomplete || MCC does this|| - || -
 
|-
 
|-
 
| How to adjust HV levels || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
 
| How to adjust HV levels || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
Line 38: Line 38:
 
| How to turn on SC target magnet || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
 
| How to turn on SC target magnet || Bill Henry/ Cameron Clarke || Incomplete || - || - || -
 
|-
 
|-
| How to move/rotate/align target || Bill Henry || Incomplete || - || - || -
+
| How to move/rotate/align target || Bill Henry || Software under devopmemt || December || - || -
 
|-
 
|-
 
| Interpreting analyzer output ||  Bill Henry/ Cameron Clarke || Incomplete || - || - || -
 
| Interpreting analyzer output ||  Bill Henry/ Cameron Clarke || Incomplete || - || - || -

Revision as of 12:06, 16 November 2018

Back to Moller jump page

PREX/CREX readiness checks for the Moller polarimeter.
Task Personnel Assigned Status Expected complete date Note Documentation link
Hardware readiness (Oversight: Simona Malace)
Survey Simona Malace Incomplete - - -
Target magnet installation Simona Malace Incomplete - - -
Target magnet alignment plan and test Simona Malace Incomplete - - -
Target foil installation Simona Malace Incomplete - - -
Target ladder installation Simona Malace Incomplete - - -
Target motion test Bill Henry Incomplete will do at time of survey Measured precision/repeatability -
Magnet cooldown test Simona Malace Incomplete - - -
Documentation/Expertise Development (Oversight: Simona Malace)
How to take a run Bill Henry/ Cameron Clarke Incomplete November - -
How to analyze a run Bill Henry/ Cameron Clarke Incomplete November - -
How to determine dead time Bill Henry/ Cameron Clarke Incomplete - - -
How to adjust thresholds Bill Henry/ Cameron Clarke Incomplete Start Dec. 2 - -
How to determine/adjust quad/dip current Bill Henry/ Cameron Clarke Incomplete MCC does this - -
How to adjust HV levels Bill Henry/ Cameron Clarke Incomplete - - -
How to turn on SC target magnet Bill Henry/ Cameron Clarke Incomplete - - -
How to move/rotate/align target Bill Henry Software under devopmemt December - -
Interpreting analyzer output Bill Henry/ Cameron Clarke Incomplete - - -
Simulation/Software Development (Oversight: Sanghwa Park)
Optics solutions for 2.22 and 0.95 GeV Bill Henry, Eric King, Sanghwa Park, Don Jones Incomplete - - -
Commissioning run plan development (Oversight: Don Jones)
SC magnet alignment plan Simona Malace Incomplete - - -
Target alignment/rotation Don Jones Incomplete - - -
Target heating Don Jones Incomplete - - -
Target centering Don Jones Incomplete - - -
Target saturation Don Jones Incomplete - - -
Quad scans Don Jones Incomplete - - -
Deadtime verification Simona Malace Incomplete - - -
Set thresholds and HV levels Simona Malace Incomplete - - -
Levchuk verification Don Jones Incomplete - - -
Sensitivity to beam parameters Don Jones Incomplete - - -
Target holding field reversal Don Jones Incomplete - - -