===  Update on MPD electronics (Paolo) ===
 
===  Update on MPD electronics (Paolo) ===
  
*
+
* just to give you a quick update about the EES production status.
 +
- All the APV front-ends have been bonded and are on the way back to EES: they have plans to start testing from the 25 of February.
 +
- I have to go there to help them to restart the test bench.
 +
- Evaristo is very welcomed to come too.
 +
- The MPD production is still pending waiting for the FPGA procurement: they claim to have found them and if everything goes well they can start assembling in 10 days from now.
 +
- I'll be in contact with them to get updates.
  
 
=== AOB ===
 
=== AOB ===

Latest revision as of 09:52, 14 February 2019

GMn GEM commissioning Meetings: Thursday 9:00am - 10:00pm

Link to all previous meetings: GMn GEM Commissioning Meeting


Kondo, ... 

Update on UVa GEM commissioning (Kondo)

Update on MPD Low voltage PS (Siyu)

Update on Comic data (Tongtong)

Update on INFN GEM commissioning (Evaristo)

  • Short update from my side:
- new GEM foils from CERN going to be delivered in CT; possibly we found the
  way to avoid the custom delay we had in the past;
- two new modules assembled will be in Rome by next week;
- continue analysis of cosmic data (slightly improved software alignment and
  analysis software) and study data reduction in firmware.

Update on MPD electronics (Paolo)

  • just to give you a quick update about the EES production status.
- All the APV front-ends have been bonded and are on the way back to EES: they have plans to start testing from the 25 of February. 
- I have to go there to help them to restart the test bench. 
- Evaristo is very welcomed to come too.
- The MPD production is still pending waiting for the FPGA procurement: they claim to have found them and if everything goes well they can start assembling in 10 days from now.
- I'll be in contact with them to get updates.