Difference between revisions of "E12-17-004-ERR-29May2019"
From Hall A Wiki
(→Agenda) |
|||
Line 14: | Line 14: | ||
== Agenda == | == Agenda == | ||
− | * (30) Executive Session | + | * (30) ''Executive Session'' |
− | * (5) Remarks from Chair and Charge | + | * (5) ''Remarks from Chair and Charge'' |
− | * (20+10) Charge Items 1, 5, 6: General overview, new equipment (beyond those in common with E12-09-019), and impact and integration with E12-09-019 run plan | + | * (20+10) '''Charge Items 1, 5, 6''': ''General overview, new equipment (beyond those in common with E12-09-019), and impact and integration with E12-09-019 run plan |
− | * (20+10) Charge Items 1, 5--8: Apparatus ownership, maintenance and control, safety documentation and procedures | + | ''* (20+10) '''Charge Items 1, 5--8''': ''Apparatus ownership, maintenance and control, safety documentation and procedures'' |
− | * (20+10) Charge Item 2, 2e, 6: E12-09-019 specific hardware, completion/commissioning schedule and tasks | + | * (20+10) '''Charge Item 2, 2e, 6''': ''E12-09-019 specific hardware, completion/commissioning schedule and tasks'' |
− | ** (20+10) Charge Item 2a: GEMs and associated electronics | + | ** (20+10) '''Charge Item 2a''': ''GEMs and associated electronics'' |
− | ** (20+10) Charge Item 2b, 2d: Charge-Exchange polarimetry hardware | + | ** (20+10) '''Charge Item 2b, 2d''': ''Charge-Exchange polarimetry hardware'' |
− | ** (20+10) Charge Item 2b, 2d: Large Angle polarimetry hardware | + | ** (20+10) '''Charge Item 2b, 2d''': ''Large Angle polarimetry hardware'' |
− | * (20+10) Charge Item 3a, 3b, 4: Simulation, analysis software and publication timeline | + | * (20+10) '''Charge Item 3a, 3b, 4''': ''Simulation, analysis software and publication timeline'' |
− | * (20+10) Charge Item 2c: Mechanical design, engineering | + | * (20+10) '''Charge Item 2c''': ''Mechanical design, engineering'' |
− | * Executive Session | + | * ''Executive Session'' |
− | * Close Out | + | * ''Close Out'' |
== Document Drafts == | == Document Drafts == |
Revision as of 22:13, 28 April 2019
Contents
E12-17-004 Experimental Readiness Review 2019 (Hall A)
Time and Location
- Date: May 29, 2019
- Location: CEBAF Center Room L102
- ERR Charge: ERR Charge
- ERR Committee: Howard Fenker (chair), Lubomir Pentchev, Chris Cuevas, Pavel Degtiarenko, Bert Manzlak, Ed Folts (observer), Javier Gomez (observer)
Agenda
- (30) Executive Session
- (5) Remarks from Chair and Charge
- (20+10) Charge Items 1, 5, 6: General overview, new equipment (beyond those in common with E12-09-019), and impact and integration with E12-09-019 run plan
* (20+10) Charge Items 1, 5--8: Apparatus ownership, maintenance and control, safety documentation and procedures
- (20+10) Charge Item 2, 2e, 6: E12-09-019 specific hardware, completion/commissioning schedule and tasks
- (20+10) Charge Item 2a: GEMs and associated electronics
- (20+10) Charge Item 2b, 2d: Charge-Exchange polarimetry hardware
- (20+10) Charge Item 2b, 2d: Large Angle polarimetry hardware
- (20+10) Charge Item 3a, 3b, 4: Simulation, analysis software and publication timeline
- (20+10) Charge Item 2c: Mechanical design, engineering
- Executive Session
- Close Out