(Update on INFN GEM commissioning (Leo, Evaristo))
(Update on INFN GEM commissioning (Leo, Evaristo))
Line 14: Line 14:
 
===  Update on INFN GEM commissioning (Leo, Evaristo) ===
 
===  Update on INFN GEM commissioning (Leo, Evaristo) ===
  
* Next visit at JLab: from Aug/21th to Sep/17th ([[Media:FrontTracker_Aug-Sep19_plan.xlsx.zip | preliminary plan (xlsx.zip)])
+
* Next visit at JLab: from Aug/21th to Sep/17th (preliminary plan: https://hallaweb.jlab.org/wiki/images/6/6c/FrontTracker_Aug-Sep19_plan.xlsx.zip)
  
 
===  Update on MPD electronics (Paolo) ===
 
===  Update on MPD electronics (Paolo) ===

Revision as of 04:51, 25 July 2019

GMn GEM commissioning Meetings: Thursday 9:00am - 10:00pm

Link to all previous meetings: GMn GEM Commissioning Meeting


Kondo, ... 

Main topic

  • Discuss preparation of the SBS Coll. Meeting / GMn, GEn-RP Preparedness Review
 very preliminary draft GEM-BB presentation (Evaristo)
  • Response to the ERR (Brad spreadsheet ..)

Update on INFN GEM commissioning (Leo, Evaristo)

Update on MPD electronics (Paolo)

Update on the Tracking efficiency / resolution (Andrew)

Update on INFN GEM commissioning (Kondo)

Tests of long HDMI cables, backplanes on teh GEM layer #3 (Thir)

Assembly of GEM layer #3 (Anu, Malinga)

Update on PREX GEM (Siyu)

AOB