Difference between revisions of "Meeting 2020 02 05"
From Hall A Wiki
(→Update on INFN GEM commissioning (Evaristo, Roberto)) |
(→Update on INFN GEM commissioning (Evaristo, Roberto)) |
||
Line 11: | Line 11: | ||
=== Update on INFN GEM commissioning (Evaristo, Roberto) === | === Update on INFN GEM commissioning (Evaristo, Roberto) === | ||
− | Evaristo could not attend the meeting today. Below is his updates from email | + | Evaristo could not attend the meeting today. Below is his updates from email |
− | * My colleagues in Catania re-tested a second GEM foil that did not passed the | + | |
− | + | * My colleagues in Catania re-tested a second GEM foil that did not passed the Quality Check in 2015. We left dry nitrogen flushing for more than 1 full day. The new test has been passed: all sector currents at 550->450 V are well below 10 nA. | |
− | + | ||
− | + | * thanks to Bogdan suggestions we prepared a new version of the GEM installation procedure (still draft), that I will distribute to Todd probably tomorrow. Essentially we are coming back to the hypothesis of using a portable crane instead of an installation stand (which would require design and manufacturing). | |
− | * thanks to Bogdan suggestions we prepared a new version of the GEM | + | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
=== Update on the Tracking efficiency / resolution (Andrew) === | === Update on the Tracking efficiency / resolution (Andrew) === |
Latest revision as of 11:04, 5 February 2020
GMn GEM commissioning Meetings: WEDNESDAY 10:00am - 11:00am
Link to all previous meetings: GMn GEM Commissioning Meeting
Kondo,
Contents
Main topic
Update on INFN GEM commissioning (Evaristo, Roberto)
Evaristo could not attend the meeting today. Below is his updates from email
- My colleagues in Catania re-tested a second GEM foil that did not passed the Quality Check in 2015. We left dry nitrogen flushing for more than 1 full day. The new test has been passed: all sector currents at 550->450 V are well below 10 nA.
- thanks to Bogdan suggestions we prepared a new version of the GEM installation procedure (still draft), that I will distribute to Todd probably tomorrow. Essentially we are coming back to the hypothesis of using a portable crane instead of an installation stand (which would require design and manufacturing).