(→Update on INFN GEM commissioning (Evaristo, Roberto)) |
(→Update on INFN GEM commissioning (Evaristo, Roberto)) |
||
Line 10: | Line 10: | ||
*- we are still waiting for the fixing of the compressor in the clean room in | *- we are still waiting for the fixing of the compressor in the clean room in | ||
Catania. | Catania. | ||
− | + | * - I just contacted Chuck for the metallic cable trays; he should be able to | |
− | + | ||
procure them in about 10 days; | procure them in about 10 days; | ||
− | + | * - due to the COVID-19 "hysteria" I am getting problem to organize the next | |
− | + | ||
visit to JLab for the SBS collaboration meeting and GEM work in clean room. | visit to JLab for the SBS collaboration meeting and GEM work in clean room. | ||
I will probably postpone the first visit. | I will probably postpone the first visit. |
Revision as of 11:05, 26 February 2020
GMn GEM commissioning Meetings: WEDNESDAY 10:00am - 11:00am
Link to all previous meetings: GMn GEM Commissioning Meeting
Kondo,
Contents
Update on INFN GEM commissioning (Evaristo, Roberto)
- - we are still waiting for the fixing of the compressor in the clean room in
Catania.
- - I just contacted Chuck for the metallic cable trays; he should be able to
procure them in about 10 days;
- - due to the COVID-19 "hysteria" I am getting problem to organize the next
visit to JLab for the SBS collaboration meeting and GEM work in clean room. I will probably postpone the first visit.