{| style="width: 90%;" | {| style="width: 90%;" | ||
|- | |- | ||
− | |'''Morning | + | |'''Thursday Morning''' |
|- | |- | ||
− | | 8:00 || ''Closed Session'' ||( | + | | 8:00 || ''Closed Session'' ||(20) || |
|- | |- | ||
− | | 8: | + | | 8:20 || Remarks from Chair and Charge || Chair (10) |
|- | |- | ||
− | | 8: | + | | 8:30 || Experiment Overview || Bogdan Wojtsekhowski (10 + 10) |
|- | |- | ||
− | | | + | | 8:50 || Charge Item 1: Design report (non-target) including modifications to beamline, SBS and detectors to accommodate polarized target || Robin Wines (20+10) |
|- | |- | ||
− | | 9: | + | | 9:20 || Charge Items 2, 3: Target overview, configuration, performance requirement. Subsystems, including cells and lasers, lessons learned and timeline || Gordon Cates (40 + 20) |
|- | |- | ||
− | | | + | |10:20 || '''Break''' || (15) |
|- | |- | ||
− | |10: | + | |10:35 || '''Charge Item 2 (target)''': Integrated System-Target Design and Fabrication || Bert Metzger (20 + 10) |
|- | |- | ||
− | | | + | |11:05 || Charge Item 3: Effect of Spectrometer fields, Magnetic Shielding and Simulation || Vladimir Nelyubin (20 + 10) |
|- | |- | ||
− | |11: | + | |11:35 || Charge Item 2 (non-target): Status of the equipment required for this experiment. Completion, commissioning. || Mark Jones (30+10) |
|- | |- | ||
− | |12: | + | |12:15 || '''Lunch''' || (45) |
|- | |- | ||
|'''Afternoon Session''' | |'''Afternoon Session''' | ||
|- | |- | ||
− | |13:00 || '''Charge | + | |13:00 || '''Charge Items 1, 2, 4''': Equipment ownership, maintenance, control. Installation plans, timeline || Jessie Butler (20 + 10) |
|- | |- | ||
− | |13:30 || '''Charge | + | |13:30 || '''Charge Item 5''': Data Analysis & Simulation, Software Status, time to 1st publication || Andrew Puckett (20+10) |
|- | |- | ||
− | |14:00 | + | |14:00 || Charge Item 6: Radiation and Shielding || TBD (20 + 10) |
|- | |- | ||
− | | 14:30 | + | |14:30 || Charge Item 7: Beam Commissioning and Machine Protections Systems || David Flay (20 + 10) |
|- | |- | ||
− | | | + | |15:00 || '''Charge Item 4''': Personpower and responsibilities || Todd Averett (20 + 10) |
|- | |- | ||
− | |15: | + | |15:30 || '''Charge Item 8''': Safety Documents, target and non-target || Jian-ping Chen, Todd Averett (15 + 5) |
|- | |- | ||
− | |15:50 || | + | |15:50 || '''Break''' || (10) |
|- | |- | ||
− | |16: | + | |16:00 || Closed Session || (90) |
− | + | ||
− | + | ||
|- | |- | ||
+ | |17:30 || Closeout || | ||
|- | |- | ||
| | | |
Revision as of 11:27, 6 October 2020
Overview
Hall A E12-09-016 (Measurement of the Neutron Electromagnetic Form Factor Ratio GEn/GMn at High Q2) Experiment Readiness Review
Experimental Readiness Review 2020
- Date: 22 October, 2020 (Thursday)
- Location: Remote
- ERR Committee
Haiyan Gao (chair),
Brian Eng (GEM), Dave Gaskell (Beam line/target), James Maxwell (Target), Yves Roblin (Beam Operation), Brad Sawatzky (Target operational experience),
Alexander Somov (Trigger), Stepan Stepanyan (Calorimeter), Chris Cuevas (Electronics),
Bert Manzlak (EHS&Q), Pavel Degtiarenko (Radiation), Ed Folts (observer), Javier Gomez (observer)
Agenda
Thursday Morning | |||
8:00 | Closed Session | (20) | |
8:20 | Remarks from Chair and Charge | Chair (10) | |
8:30 | Experiment Overview | Bogdan Wojtsekhowski (10 + 10) | |
8:50 | Charge Item 1: Design report (non-target) including modifications to beamline, SBS and detectors to accommodate polarized target | Robin Wines (20+10) | |
9:20 | Charge Items 2, 3: Target overview, configuration, performance requirement. Subsystems, including cells and lasers, lessons learned and timeline | Gordon Cates (40 + 20) | |
10:20 | Break | (15) | |
10:35 | Charge Item 2 (target): Integrated System-Target Design and Fabrication | Bert Metzger (20 + 10) | |
11:05 | Charge Item 3: Effect of Spectrometer fields, Magnetic Shielding and Simulation | Vladimir Nelyubin (20 + 10) | |
11:35 | Charge Item 2 (non-target): Status of the equipment required for this experiment. Completion, commissioning. | Mark Jones (30+10) | |
12:15 | Lunch | (45) | |
Afternoon Session | |||
13:00 | Charge Items 1, 2, 4: Equipment ownership, maintenance, control. Installation plans, timeline | Jessie Butler (20 + 10) | |
13:30 | Charge Item 5: Data Analysis & Simulation, Software Status, time to 1st publication | Andrew Puckett (20+10) | |
14:00 | Charge Item 6: Radiation and Shielding | TBD (20 + 10) | |
14:30 | Charge Item 7: Beam Commissioning and Machine Protections Systems | David Flay (20 + 10) | |
15:00 | Charge Item 4: Personpower and responsibilities | Todd Averett (20 + 10) | |
15:30 | Charge Item 8: Safety Documents, target and non-target | Jian-ping Chen, Todd Averett (15 + 5) | |
15:50 | Break | (10) | |
16:00 | Closed Session | (90) | |
17:30 | Closeout | ||
Draft of COO (pdf) | |||
Draft of ERG (pdf) and chart (pdf) | |||
Draft of ESAD (pdf) NEEDS UPDATE | |||
Input for RSAD from Radcon (radiation budget form) (pdf) and (pdf) NEEDS UPDATE | |||
Draft of OSP for GEM detectors (pdf) | |||
Draft of OSP for BigBite magnet (pdf) | |||
Draft of OSP for BigBite rotation (pdf) | |||
Draft of OSP GRINCH Cherenkov detector (pdf) | |||
Draft of OSP for BigBite timing hodoscope (pdf) | |||
Draft of OSP for Hadron Calorimeter, HCal-J (pdf) | |||
Draft of OSP for Coordinate Detector, CDet (pdf) |