Line 1: | Line 1: | ||
+ | *Updates | ||
+ | **HCal | ||
+ | **Bigbite Shower | ||
+ | **Bigbite Hodoscope | ||
+ | **GRINCH | ||
+ | **LHRS | ||
+ | **CDet | ||
+ | **GEM BB Hall A | ||
+ | **GEM INFN Test Lab | ||
+ | **GEM UVA | ||
+ | **Beamline | ||
+ | **Helicity | ||
+ | **HV | ||
+ | **Scalers | ||
+ | |||
+ | |||
*On-going tasks | *On-going tasks | ||
**Network setup ( done ) | **Network setup ( done ) |
Revision as of 10:29, 30 July 2021
- Updates
- HCal
- Bigbite Shower
- Bigbite Hodoscope
- GRINCH
- LHRS
- CDet
- GEM BB Hall A
- GEM INFN Test Lab
- GEM UVA
- Beamline
- Helicity
- HV
- Scalers
- On-going tasks
- Network setup ( done )
- Scaler crate setup (75 % - need put crate in / setup cpu )
- 3 rd GEM VXS crate install router moved up ( 75% )
- need power and network in GEM bunker
- detector accounts setup
- boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
- detector cabling
- new MPD production - about to start - need to ship our FPGA to Paolo
- MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
- Bigbite - HCal trigger setup
- TS setup - 0%
- Beamline crate setup ( in scaler crate )
- HCAL cabling
- HCAL need power
- Mark hodoscope trigger ?
- Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
- LHRS fiber pull
- Outstanding issues
- 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
- SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
- need to adjust for HCAL transit time with different PMTs
- status of cosmics paddles
- GEM fibers too short : 60 m ordered
- 15 bad MPDs