− | On-going tasks | + | *Updates |
− | Network setup ( done ) | + | **HCal |
− | Scaler crate setup (75 % - need put crate in / setup cpu ) | + | ***Cables from FE to bunker : about 20% done ~ 2weeks to complete - could use man power to unroll cable while 2 people installing |
− | 3 rd GEM VXS crate install router moved up ( 75% ) | + | ***5 to 9 Sebastian and Provokar out of town |
− | need power and network in GEM bunker | + | ***power to HCAL racks - still no power - issue with transformer - Jack thinks transformer might not have enough power |
− | detector accounts setup | + | **Bigbite Shower |
− | boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers) | + | ***starting laying cable |
− | detector cabling | + | ***HV cables were found to be to short ( 25 m - need 30 m) - 10 m extension found - making more extensions - signals cables not laid out |
− | new MPD production - about to start - need to ship our FPGA to Paolo | + | ***HV location changed |
− | MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot | + | ***BB shower VXS |
− | Bigbite - HCal trigger setup | + | **Bigbite Hodoscope |
− | TS setup - 0% | + | ***working in Hall staging cables : ADC cables in bunker ready to be plug when BB cable tray is installed, waiting for cable tray for detector to bunker |
− | Beamline crate setup ( in scaler crate ) | + | ***Rachel and David working on SBS-Offline software |
− | HCAL cabling | + | **GRINCH |
− | HCAL need power | + | ***Fully cabled : ADC and TDC at both ends, some slack left in middle way, can adjust if needed |
− | Mark hodoscope trigger ? | + | ***ADC cables on detector |
− | Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne | + | ***just need HV to take data |
− | Outstanding issues | + | ***LV cable needs to be extended for NINO supply |
− | 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC | + | ***some cables connectors need to be repaired |
− | SD delay : still need | + | ***will setup GRINCH CODA on counting house computer |
− | need to adjust for HCAL transit time with different PMTs | + | ***repeater rack is in bunker - 100 m TDC cables |
− | status of cosmics paddles | + | **LHRS |
− | GEM fibers too short : | + | ***Maria plots of A1 |
+ | ***VDC maybe one bad card : Jack knows about it | ||
+ | ***Scaler server from Steve setup for both crates | ||
+ | ***Scaler ordered postponed to Oct 1 | ||
+ | **CDet | ||
+ | ***taking data, fixing problems | ||
+ | ***identified replacement PMTs | ||
+ | ***HV still running | ||
+ | **GEM BB Hall A | ||
+ | ***fibers setup | ||
+ | ***LV ready | ||
+ | ***can power up on Monday | ||
+ | ***Bryan get closer to completion, Ben showed ROC part working for FADC | ||
+ | ***ready next week for VTP in Hall A if needed | ||
+ | **GEM INFN Test Lab | ||
+ | ***Test SSP readout | ||
+ | **GEM UVA | ||
+ | ***working on shielding | ||
+ | **Beamline | ||
+ | ***software, monitoring scripts almost setup, writing shifter documentation | ||
+ | ***looking at PREX alarm handler | ||
+ | **Helicity | ||
+ | ***Bob and Paul, will go in LHRS to install scalers - One scaler has a bad user bit 2 and on has a broken NIM input - could use ECL - ECL scaler - could use one scaler from scaler crate at entrance of hall | ||
+ | ***work on analysis software TQWeak class compatible and should be | ||
+ | **HV | ||
+ | **Scalers | ||
+ | ***2eVME | ||
+ | ***Crate to be installed under hodoscope | ||
+ | *VME controllers | ||
+ | **Bryan helping set up, most should be up in a few days | ||
+ | |||
+ | |||
+ | |||
+ | *On-going tasks | ||
+ | **Network setup ( done ) | ||
+ | **Scaler crate setup (75 % - need put crate in / setup cpu ) | ||
+ | **3 rd GEM VXS crate install router moved up ( 75% ) | ||
+ | **need power and network in GEM bunker | ||
+ | **detector accounts setup ( check with Ole ) | ||
+ | **boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers) | ||
+ | **detector cabling - | ||
+ | **new MPD production - about to start - need to ship our FPGA to Paolo | ||
+ | **MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot | ||
+ | **setup portservers | ||
+ | **need to install remote switch for crate in bunker - rest are VXS or VME64 | ||
+ | **Bigbite - HCal trigger setup | ||
+ | **TS setup - 0% | ||
+ | **Beamline crate setup ( in scaler crate ) | ||
+ | **HCAL cabling | ||
+ | **HCAL need power | ||
+ | **Mark hodoscope trigger ? | ||
+ | **Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne | ||
+ | **LHRS fiber pull | ||
+ | |||
+ | |||
+ | *Outstanding issues | ||
+ | **2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC | ||
+ | **SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) | ||
+ | **need to adjust for HCAL transit time with different PMTs | ||
+ | **status of cosmics paddles ( installed by Bogdan ) | ||
+ | **GEM fibers too short : 60 m ordered | ||
+ | **15 bad MPDs |
Latest revision as of 11:27, 30 July 2021
- Updates
- HCal
- Cables from FE to bunker : about 20% done ~ 2weeks to complete - could use man power to unroll cable while 2 people installing
- 5 to 9 Sebastian and Provokar out of town
- power to HCAL racks - still no power - issue with transformer - Jack thinks transformer might not have enough power
- Bigbite Shower
- starting laying cable
- HV cables were found to be to short ( 25 m - need 30 m) - 10 m extension found - making more extensions - signals cables not laid out
- HV location changed
- BB shower VXS
- Bigbite Hodoscope
- working in Hall staging cables : ADC cables in bunker ready to be plug when BB cable tray is installed, waiting for cable tray for detector to bunker
- Rachel and David working on SBS-Offline software
- GRINCH
- Fully cabled : ADC and TDC at both ends, some slack left in middle way, can adjust if needed
- ADC cables on detector
- just need HV to take data
- LV cable needs to be extended for NINO supply
- some cables connectors need to be repaired
- will setup GRINCH CODA on counting house computer
- repeater rack is in bunker - 100 m TDC cables
- LHRS
- Maria plots of A1
- VDC maybe one bad card : Jack knows about it
- Scaler server from Steve setup for both crates
- Scaler ordered postponed to Oct 1
- CDet
- taking data, fixing problems
- identified replacement PMTs
- HV still running
- GEM BB Hall A
- fibers setup
- LV ready
- can power up on Monday
- Bryan get closer to completion, Ben showed ROC part working for FADC
- ready next week for VTP in Hall A if needed
- GEM INFN Test Lab
- Test SSP readout
- GEM UVA
- working on shielding
- Beamline
- software, monitoring scripts almost setup, writing shifter documentation
- looking at PREX alarm handler
- Helicity
- Bob and Paul, will go in LHRS to install scalers - One scaler has a bad user bit 2 and on has a broken NIM input - could use ECL - ECL scaler - could use one scaler from scaler crate at entrance of hall
- work on analysis software TQWeak class compatible and should be
- HV
- Scalers
- 2eVME
- Crate to be installed under hodoscope
- HCal
- VME controllers
- Bryan helping set up, most should be up in a few days
- On-going tasks
- Network setup ( done )
- Scaler crate setup (75 % - need put crate in / setup cpu )
- 3 rd GEM VXS crate install router moved up ( 75% )
- need power and network in GEM bunker
- detector accounts setup ( check with Ole )
- boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
- detector cabling -
- new MPD production - about to start - need to ship our FPGA to Paolo
- MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
- setup portservers
- need to install remote switch for crate in bunker - rest are VXS or VME64
- Bigbite - HCal trigger setup
- TS setup - 0%
- Beamline crate setup ( in scaler crate )
- HCAL cabling
- HCAL need power
- Mark hodoscope trigger ?
- Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
- LHRS fiber pull
- Outstanding issues
- 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
- SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
- need to adjust for HCAL transit time with different PMTs
- status of cosmics paddles ( installed by Bogdan )
- GEM fibers too short : 60 m ordered
- 15 bad MPDs