Difference between revisions of "August 6th 2021"

From Hall A Wiki
Jump to: navigation, search
 
(2 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
*Updates
 
*Updates
 
**HCal
 
**HCal
***Cables from FE to bunker : about 20% done ~ 2weeks to complete - could use man power to unroll cable while 2 people installing
+
***still cabling - 9 bundles
***5 to 9 Sebastian and Provokar out of town
+
***32 cables additionnal + 32 spares channels
***power to HCAL racks - still no power - issue with transformer - Jack thinks transformer might not have enough power
+
***slack to be moved to HCAL side : difficult process on-going - might take a few days
 +
***hope to be done next week
 
**Bigbite Shower
 
**Bigbite Shower
***starting laying cable
+
***finished HV cables
***HV cables were found to be to short ( 25 m - need 30 m) - 10 m extension found - making more extensions - signals cables not laid out
+
***working signal cables and trigger monitor
***HV location changed
+
***preshower finished on BB, shower cabling but others can use platform
***BB shower VXS
+
 
**Bigbite Hodoscope
 
**Bigbite Hodoscope
***working in Hall staging cables : ADC cables in bunker ready to be plug when BB cable tray is installed, waiting for cable tray for detector to bunker
+
***were waiting for cable trays - in place now - will start lying cables ADC and TDC
***Rachel and David working on SBS-Offline software
+
*** software progress
 +
*** Level translator can be powered
 
**GRINCH
 
**GRINCH
***Fully cabled : ADC and TDC at both ends, some slack left in middle way, can adjust if needed
+
***moved all slack near BigBite
***ADC cables on detector
+
***HV cables : patch, can install long HV cables , HV cables at top of BB, need lift and will install TDC at same side
***just need HV to take data
+
***LV cable needs to be extended for NINO supply
+
***some cables connectors need to be repaired
+
***will setup GRINCH CODA on counting house computer
+
***repeater rack is in bunker - 100 m TDC cables
+
 
**LHRS
 
**LHRS
***Maria plots of A1
+
***almost ready, a few missing channels
***VDC maybe one bad card : Jack knows about it
+
***Bob will help Ole in counting room - 2 weeks - might need more people
***Scaler server from Steve setup for both crates
+
***Scaler ordered postponed to Oct 1
+
 
**CDet
 
**CDet
***taking data, fixing problems
+
***student working on analysis with new students
***identified replacement PMTs
+
***working on resistors and taking data
***HV still running
+
*** 1.5 module left to go
 +
*** some PMT ordered
 
**GEM BB Hall A
 
**GEM BB Hall A
***fibers setup
+
***gas flowing on BB side
***LV ready
+
***LV connection on-going
***can power up on Monday
+
***HV ready
***Bryan get closer to completion, Ben showed ROC part working for FADC
+
***checking connection : MPD fine, possibly one broken fiber
***ready next week for VTP in Hall A if needed
+
***few spare lines avalaible
 +
***almost ready for readout
 +
***shielding : not solid plan for INFN in BigBite - could not run HV on chamber - making improvements adding kapton - ~2 days of trouble shooting
 +
***SSP readout almost done with CODA - should be avalaible at end of day - running on adaq1
 +
***need to update SSP in Hall A
 
**GEM INFN Test Lab
 
**GEM INFN Test Lab
***Test SSP readout
+
***J1 all shielding, J3 half installed
 +
***SSP readout in INFN all up to date and running
 
**GEM UVA
 
**GEM UVA
***working on shielding
 
 
**Beamline
 
**Beamline
***software, monitoring scripts almost setup, writing shifter documentation
+
***working on live plots for shift takers
***looking at PREX alarm handler
+
***hacsbc2
 +
***run copy to SBS bunker 
 
**Helicity
 
**Helicity
***Bob and Paul, will go in LHRS to install scalers - One scaler has a bad user bit 2 and on has a broken NIM input - could use ECL - ECL scaler - could use one scaler from scaler crate at entrance of hall
+
***helicity scaler installed on LHRS - was working in test setup
***work on analysis software TQWeak class compatible and should be
+
***
 +
**RF time
 +
***need to connect in LHRS and send copy to
 
**HV
 
**HV
 +
***rpi online : GRINCH and shower should be ok
 +
***BB hodoscope need to be powered - same extension
 +
***MPOD installed - need to set it up on network
 +
***EPICS software avalaible for all
 +
***rpi17 and rpi18 off now - but can be turned one
 
**Scalers
 
**Scalers
***2eVME
+
***crate for scalers installed
***Crate to be installed under hodoscope
+
***working on software to handle different scalers
*VME controllers  
+
***can turn on FADC scalers but depends on thresholds
**Bryan helping set up, most should be up in a few days
+
***scaler server run during run and between run
 +
***shower scalers can go in scaler crate if not there already
 +
**VME controllers
 +
***all VME controllers booted for shower, hodoscope and GEM, GRINCH
 +
 +
 
  
  
  
 
*On-going tasks
 
*On-going tasks
**Network setup ( done )
+
**Network setup ( done ) - SBS MPD side might need few cables
**Scaler crate setup (75 % - need put crate in / setup cpu )
+
**Scaler crate setup (50 % - Steve ) - need fix supply
**3 rd GEM VXS crate install router moved up ( 75%  )
+
**documentation of VME crate names to power cycle
**need power and network in GEM bunker
+
**3 rd GEM VXS crate install router moved up ( 50%  )
**detector accounts setup ( check with Ole )
+
**need power and network in GEM bunker ( done ) - need connect computer
**boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
+
**detector accounts - will just use vncservers on different machines -
**detector cabling -
+
**boot VME controllers (90 % done - need ask hostname TS crate )
**new MPD production - about to start - need to ship our FPGA to Paolo
+
**TS cables - all fibers plugged - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS
**MPD VTP readout - on-going in daq lab - being setup  in Hall A - need setup VTPs to boot
+
**detector cabling  
**setup portservers
+
**new MPD production - about to start - FPGA shipped to Paolo
**need to install remote switch for crate in bunker - rest are VXS or VME64
+
**MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link
**Bigbite - HCal trigger setup
+
**MPD being setup  in Hall A - need setup VTPs to boot - 10 gigE network plugged - will be able to test in Hall A - LV installed soon
**TS setup - 0%
+
**setup portservers : 1 4 port portserver for VTP, still need to set up a 8 port one and HCAL portserver
**Beamline crate setup ( in scaler crate )  
+
**need to install remote switch for crate in bunker - rest are VXS or VME64 -
 +
**Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install
 +
**TS setup - 50 %
 +
**Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup
 
**HCAL cabling  
 
**HCAL cabling  
**HCAL need power  
+
**HCAL need power ( done, Berta )
 
**Mark hodoscope trigger ?
 
**Mark hodoscope trigger ?
**Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
+
**Computer move to Hall A : sbsdaq1/2 tedbbdaq (done ) enpcamsonne ( will move next week )
**LHRS fiber pull  
+
**LHRS fiber pull ( waiting fiber August 13th ) - most likely LHRS at end of SBS run
 
+
**BPM/BCM cables SBS weldment ( will do next week )
  
 
*Outstanding issues
 
*Outstanding issues
**2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC  
+
**2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare  ( done )
 
**SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
 
**SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
 
**need to adjust for HCAL transit time with different PMTs
 
**need to adjust for HCAL transit time with different PMTs
 
**status of cosmics paddles ( installed by Bogdan )
 
**status of cosmics paddles ( installed by Bogdan )
**GEM fibers too short : 60 m ordered
+
**GEM fibers too short : Mark will order parts
**15 bad MPDs
+
**15 bad MPDs - need to look at fixing  - Ben ?  Dustin loaning us 6 MPDs - need 85 total - 67 in hand
 +
***APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir )
 +
**GEM fiber possibly bad
 +
**GEM HV IP need setup ( Alex )

Latest revision as of 11:36, 6 August 2021

  • Updates
    • HCal
      • still cabling - 9 bundles
      • 32 cables additionnal + 32 spares channels
      • slack to be moved to HCAL side : difficult process on-going - might take a few days
      • hope to be done next week
    • Bigbite Shower
      • finished HV cables
      • working signal cables and trigger monitor
      • preshower finished on BB, shower cabling but others can use platform
    • Bigbite Hodoscope
      • were waiting for cable trays - in place now - will start lying cables ADC and TDC
      • software progress
      • Level translator can be powered
    • GRINCH
      • moved all slack near BigBite
      • HV cables : patch, can install long HV cables , HV cables at top of BB, need lift and will install TDC at same side
    • LHRS
      • almost ready, a few missing channels
      • Bob will help Ole in counting room - 2 weeks - might need more people
    • CDet
      • student working on analysis with new students
      • working on resistors and taking data
      • 1.5 module left to go
      • some PMT ordered
    • GEM BB Hall A
      • gas flowing on BB side
      • LV connection on-going
      • HV ready
      • checking connection : MPD fine, possibly one broken fiber
      • few spare lines avalaible
      • almost ready for readout
      • shielding : not solid plan for INFN in BigBite - could not run HV on chamber - making improvements adding kapton - ~2 days of trouble shooting
      • SSP readout almost done with CODA - should be avalaible at end of day - running on adaq1
      • need to update SSP in Hall A
    • GEM INFN Test Lab
      • J1 all shielding, J3 half installed
      • SSP readout in INFN all up to date and running
    • GEM UVA
    • Beamline
      • working on live plots for shift takers
      • hacsbc2
      • run copy to SBS bunker
    • Helicity
      • helicity scaler installed on LHRS - was working in test setup
    • RF time
      • need to connect in LHRS and send copy to
    • HV
      • rpi online : GRINCH and shower should be ok
      • BB hodoscope need to be powered - same extension
      • MPOD installed - need to set it up on network
      • EPICS software avalaible for all
      • rpi17 and rpi18 off now - but can be turned one
    • Scalers
      • crate for scalers installed
      • working on software to handle different scalers
      • can turn on FADC scalers but depends on thresholds
      • scaler server run during run and between run
      • shower scalers can go in scaler crate if not there already
    • VME controllers
      • all VME controllers booted for shower, hodoscope and GEM, GRINCH



  • On-going tasks
    • Network setup ( done ) - SBS MPD side might need few cables
    • Scaler crate setup (50 % - Steve ) - need fix supply
    • documentation of VME crate names to power cycle
    • 3 rd GEM VXS crate install router moved up ( 50% )
    • need power and network in GEM bunker ( done ) - need connect computer
    • detector accounts - will just use vncservers on different machines -
    • boot VME controllers (90 % done - need ask hostname TS crate )
    • TS cables - all fibers plugged - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS
    • detector cabling
    • new MPD production - about to start - FPGA shipped to Paolo
    • MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link
    • MPD being setup in Hall A - need setup VTPs to boot - 10 gigE network plugged - will be able to test in Hall A - LV installed soon
    • setup portservers : 1 4 port portserver for VTP, still need to set up a 8 port one and HCAL portserver
    • need to install remote switch for crate in bunker - rest are VXS or VME64 -
    • Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install
    • TS setup - 50 %
    • Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup
    • HCAL cabling
    • HCAL need power ( done, Berta )
    • Mark hodoscope trigger ?
    • Computer move to Hall A : sbsdaq1/2 tedbbdaq (done ) enpcamsonne ( will move next week )
    • LHRS fiber pull ( waiting fiber August 13th ) - most likely LHRS at end of SBS run
    • BPM/BCM cables SBS weldment ( will do next week )
  • Outstanding issues
    • 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done )
    • SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
    • need to adjust for HCAL transit time with different PMTs
    • status of cosmics paddles ( installed by Bogdan )
    • GEM fibers too short : Mark will order parts
    • 15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand
      • APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir )
    • GEM fiber possibly bad
    • GEM HV IP need setup ( Alex )