Line 10: | Line 10: | ||
=== Update on BB GEMs(Sean, Ezekiel, Holly, Anu) === | === Update on BB GEMs(Sean, Ezekiel, Holly, Anu) === | ||
− | * | + | * We cannot use pedestal plots as indicators of APVs that are disconnected (see email). |
+ | * [https://sbs.jlab.org/DocDB/0001/000167/003/Neg_pulse_tracking_3_7_22.pdf Negative signal tracking study] | ||
+ | ** HALOG with all plots - https://logbooks.jlab.org/entry/3986717 | ||
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) === | === Update on UVa GEM layers for GEn-RP (Anu, John, Thir) === | ||
− | * [https:// | + | *Still having issues with "gaps" or "dead zones" on inline layers |
+ | **Possible trigger issues?? Need to step through the system and scope/check It out | ||
+ | **Need to get as many GEMs/APVs up as possible to rule out any effects due to tracking. | ||
+ | *Connection issues with APVs on Inline Layer 3 - G3 | ||
+ | **We slid the layer out and re-attached/assessed the connection of the 12-slot | ||
+ | **Replaced the APV on Inline Layer 4 G0 12-slot. Inline Layer 3 and 4 are on the same frame. | ||
+ | |||
+ | |||
+ | *[https://hallaweb.jlab.org/wiki/images/2/28/EEL_125_GEM_DAQ_updates.pdf EEL 125 GEM DAQ updates] | ||
=== Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) === | === Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) === | ||
* HV divider upgrade for INFN GEMs | * HV divider upgrade for INFN GEMs | ||
* [https://hallaweb.jlab.org/wiki/images/6/60/Parallel_divider_first-test.pdf First test of parallel divider] | * [https://hallaweb.jlab.org/wiki/images/6/60/Parallel_divider_first-test.pdf First test of parallel divider] | ||
+ | *[https://hallaweb.jlab.org/wiki/index.php/File:cluster_1943.pdf Cosmic Run 1943] | ||
+ | *[https://hallaweb.jlab.org/wiki/index.php/File:cluster_1974.pdf Cosmic Run 1974] | ||
=== DAQ updates (Ben, Bryan, Alex) === | === DAQ updates (Ben, Bryan, Alex) === |
Latest revision as of 10:32, 16 March 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan (all)
- Installation of HV dividers on BB: April 18 for 3 weeks, upgraded dividers on back tracker and active on front 3 layers
Update on BB GEMs(Sean, Ezekiel, Holly, Anu)
- We cannot use pedestal plots as indicators of APVs that are disconnected (see email).
- Negative signal tracking study
- HALOG with all plots - https://logbooks.jlab.org/entry/3986717
Update on UVa GEM layers for GEn-RP (Anu, John, Thir)
- Still having issues with "gaps" or "dead zones" on inline layers
- Possible trigger issues?? Need to step through the system and scope/check It out
- Need to get as many GEMs/APVs up as possible to rule out any effects due to tracking.
- Connection issues with APVs on Inline Layer 3 - G3
- We slid the layer out and re-attached/assessed the connection of the 12-slot
- Replaced the APV on Inline Layer 4 G0 12-slot. Inline Layer 3 and 4 are on the same frame.
Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)
- HV divider upgrade for INFN GEMs
- First test of parallel divider
- Cosmic Run 1943
- Cosmic Run 1974
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A