Difference between revisions of "Meeting 2022 09 14"
From Hall A Wiki
(→Near term work plan) |
|||
Line 7: | Line 7: | ||
=== Near term work plan === | === Near term work plan === | ||
− | |||
− | |||
* SBS DAQ integration to GEn-II | * SBS DAQ integration to GEn-II | ||
* Online monitoring and SBS-offline preparation for GEn-II | * Online monitoring and SBS-offline preparation for GEn-II | ||
Line 18: | Line 16: | ||
* see the GEM commissioning run plan for GEn-II here: [https://docs.google.com/spreadsheets/d/1ONOpMdQAgFz6FKP5G605jyuHiWJ1Sv1HHhwWhHg7GnI/edit#gid=0] | * see the GEM commissioning run plan for GEn-II here: [https://docs.google.com/spreadsheets/d/1ONOpMdQAgFz6FKP5G605jyuHiWJ1Sv1HHhwWhHg7GnI/edit#gid=0] | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
* Thoughts on special run requests during GEn: | * Thoughts on special run requests during GEn: | ||
** Luminosity studies (Nilanga) | ** Luminosity studies (Nilanga) |
Revision as of 10:40, 14 September 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan
- SBS DAQ integration to GEn-II
- Online monitoring and SBS-offline preparation for GEn-II
- Documentation update
- CAEN HV Module paper work
- see the GEM commissioning run plan for GEn-II here: [1]
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
Update on BB GEMs
- Cosmic data taken this week and GEMs remain stable.
- Ben investigating 3 ADC difference in CM calculation in the firmware.
- Cleaning up online monitoring for GEn
Update on INFN GEM layers for GEn-RP
- Issue with APVs in SBS setup. Running disabled at the moment to stabilize DAQ.
Update on UVa GEM layers for GEn-RP
John:
- All layers/modules of SBS stack are operational and taking data.
- Further latency adjustments improved hits and efficiencies