Difference between revisions of "Meeting 2022 11 16"
From Hall A Wiki
(→Update on layers for GEn-RP) |
(→Update on BB GEMs) |
||
(One intermediate revision by one other user not shown) | |||
Line 10: | Line 10: | ||
=== Update on BB GEMs === | === Update on BB GEMs === | ||
− | * Layer | + | * Layer 2 giving lower efficiency than naively expected. Nothing obvious in all detector performance plots. Likely due to some software thresholds added during pass change. |
− | * | + | ** Will investigate further. |
+ | * Still need luminosity scan, and BBL0 iteration check (with Nilanga) | ||
=== Update on layers for GEn-RP === | === Update on layers for GEn-RP === |
Latest revision as of 11:31, 16 November 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Commissioning of the GEMs:
- See: [1]
Update on BB GEMs
- Layer 2 giving lower efficiency than naively expected. Nothing obvious in all detector performance plots. Likely due to some software thresholds added during pass change.
- Will investigate further.
- Still need luminosity scan, and BBL0 iteration check (with Nilanga)
Update on layers for GEn-RP
- Stand alone DAQ:
- INFN LV?
- need to keep running and monitor crashes
- hv scan in parallel daq?
- NDX probe installed in SBS electronics bunker