* SBS side LV:
 
* SBS side LV:
** Ellen to install some controller and readback (in progress)
+
** Ellen to network for browser access (in progress)
  
 
* SBS GEMs:
 
* SBS GEMs:
Line 13: Line 13:
 
* Clean up our areas: move our stuff out of the Hall (in progress)
 
* Clean up our areas: move our stuff out of the Hall (in progress)
 
* Update channels in the alarm handler
 
* Update channels in the alarm handler
 +
* High voltage cables?!

Revision as of 21:54, 2 April 2024

  • SBS side LV:
    • Ellen to network for browser access (in progress)
  • SBS GEMs:
    • techs to install final shielding block around the electronics hut
    • Finish cabling, low level testing, cosmics (in progress)
  • BB GEMs:
    • Finish cabling, low level testing, cosmics (in progress)
  • Update the documentation on the HV and LV operations (before beam)
  • GEM experts on call (in progress)
  • Clean up our areas: move our stuff out of the Hall (in progress)
  • Update channels in the alarm handler
  • High voltage cables?!