* SBS side LV:
 
* SBS side LV:
** Joe to connect, instruct on controls (DONE!)
+
** Ellen to network for browser access (in progress)
** Ellen to install some controller and readback (in progress, Ellen working with accelerator)
+
** Input the jumpers on the breakout panel (DONE!)
+
** Run the cables (in progress, Armen adding connectors)
+
  
 
* SBS GEMs:
 
* SBS GEMs:
** Install XW into stack (DONE!)
+
** Cosmics (in progress)
** Finish signal cabling (asap)
+
** Connect to HV patches (after HDMI cabling complete)
+
** reconnect gas to RP layers (after BB XY work?)
+
** techs to install final shielding blocks around the electronics hut
+
  
 
* BB GEMs:
 
* BB GEMs:
** Upgrade the XY HV, re-install (would like to have SBS troubleshooting going on at the same time so as not to hold this up)
+
** Cosmics (in progress)
  
* Readout:
+
* Update the documentation on the HV and LV operations (in progress)
** Balance VTP fibers amongst crates to optimize (after GEMs are installed)
+
* Update the GEM reset GUI
** Ensure that reboot/troubleshooting script works for all crates (DONE!)
+
* GEM experts on call (please sign up!)
 
+
* Clean up our areas: move our stuff out of the Hall (done?)
* High voltage:
+
* Update channels in the alarm handler (status?)
** Finish channels in GUI (DONE!)
+
* High voltage cables?! (status/tests?)
** move HV to working reboot strip (done, but need to add to gui)
+
** finalize script for GUI upload of HV and operation (DONE!)
+
 
+
* Update the documentation on the HV and LV operations (before beam)
+
* GEM experts on call (setup before beam)
+
* Clean up our areas (should start now, little by little)
+

Latest revision as of 12:31, 9 April 2024

  • SBS side LV:
    • Ellen to network for browser access (in progress)
  • SBS GEMs:
    • Cosmics (in progress)
  • BB GEMs:
    • Cosmics (in progress)
  • Update the documentation on the HV and LV operations (in progress)
  • Update the GEM reset GUI
  • GEM experts on call (please sign up!)
  • Clean up our areas: move our stuff out of the Hall (done?)
  • Update channels in the alarm handler (status?)
  • High voltage cables?! (status/tests?)