<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span>
 
 
Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.php/GMn_GEM_Commissioning_Meeting GMn GEM Commissioning Meeting]
 
 
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
 
----
 
 
<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span>
 
<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span>
  
Line 12: Line 6:
 
----
 
----
 
=== Progress from this past week ===
 
=== Progress from this past week ===
* We have ran up the HV on L0, L1, L2, L3, L4M1 and L5M1/2/3. [https://logbooks.jlab.org/entry/4311939][https://logbooks.jlab.org/entry/4312015] The HV test indicates shorts in L3M3 foil G3 and L1 XW foil G1. We held the other GEMs at the 3650V for 5-10 minutes for observation.
+
* We have ran up the HV on L0, L1, L2, L3, L4, L5, L6, and L8. [https://logbooks.jlab.org/entry/4311877][https://logbooks.jlab.org/entry/4311939][https://logbooks.jlab.org/entry/4312015][https://logbooks.jlab.org/entry/4312109] The HV test indicates shorts in L3M3 foil G3, L1 XW foil G1, and L6(M0 and/or M1) foil G2. We held the other GEMs at the 3650V for 5-10 minutes for observation.
*
+
* There will be a power outage on Thursday morning[https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=20], which will also affect the Hall A gas shed.
 
*
 
*
  

Latest revision as of 15:08, 9 July 2024

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Progress from this past week

  • We have ran up the HV on L0, L1, L2, L3, L4, L5, L6, and L8. [1][2][3][4] The HV test indicates shorts in L3M3 foil G3, L1 XW foil G1, and L6(M0 and/or M1) foil G2. We held the other GEMs at the 3650V for 5-10 minutes for observation.
  • There will be a power outage on Thursday morning[5], which will also affect the Hall A gas shed.

GEp preparations

  • Our GEM task list is here: workplan
  • Remove layers, isolate shorted sectors, repair APVs as needed
  • Joe B will add LV inputs for new GEMs in the stack, we will need to make those cables (4 more layers)
  • Install BB gas distribution from SBS line -- DSG will do this
  • Further calibrations of SBS gas mix
  • Install BB electronics crates and MPDs in new location
  • Prepare and install pixel layers
  • Repair/troubleshoot problematic CAEN crates -- DSG working on this
  • MPD testing and repair (we should do this now in test lab, who can coordinate?)

DAQ updates (Ben, Bryan, Alex)

  • Implement and test histogram method


https://redmine.jlab.org/projects/sbs-daq-gep-gems/issues