Difference between revisions of "Summer 2011 Activity Log"

From Hall A Wiki
Jump to: navigation, search
(New page: May 23-27 Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab. May 31-J...)
 
 
(2 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
May 23-27
 
May 23-27
 +
 
Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab.
 
Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab.
  
May 31-June3
+
 
Resoldered GEM voltage dividers.
+
May 31-June 3
 +
 
 +
Resoldered GEM voltage dividers. Nick created 2 macros to look at pedestals and RMS. Still need to have it look ad total ADC and have a GUI to look at 1 channel, and not 2D.
 +
 
 +
 
 +
June 6-10
 +
 
 +
Fixed the trigger signal. Set up data lines from GEMs. Fixed Hold/Clear/Clock signals.
 +
 
 +
 
 +
June

Latest revision as of 09:49, 15 June 2011

May 23-27

Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab.


May 31-June 3

Resoldered GEM voltage dividers. Nick created 2 macros to look at pedestals and RMS. Still need to have it look ad total ADC and have a GUI to look at 1 channel, and not 2D.


June 6-10

Fixed the trigger signal. Set up data lines from GEMs. Fixed Hold/Clear/Clock signals.