Difference between revisions of "Summer 2011 Activity Log"
From Hall A Wiki
(One intermediate revision by the same user not shown) | |||
Line 3: | Line 3: | ||
Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab. | Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab. | ||
− | |||
− | Resoldered GEM voltage dividers. | + | May 31-June 3 |
+ | |||
+ | Resoldered GEM voltage dividers. Nick created 2 macros to look at pedestals and RMS. Still need to have it look ad total ADC and have a GUI to look at 1 channel, and not 2D. | ||
+ | |||
+ | |||
+ | June 6-10 | ||
+ | |||
+ | Fixed the trigger signal. Set up data lines from GEMs. Fixed Hold/Clear/Clock signals. | ||
+ | |||
+ | |||
+ | June |
Latest revision as of 09:49, 15 June 2011
May 23-27
Set up trigger logic with 2 Scintillators and a lead glass calorimeter. Wiki updated with wiring diagram. Fixed leaking regulator valve for Gas. Set up computer in lab.
May 31-June 3
Resoldered GEM voltage dividers. Nick created 2 macros to look at pedestals and RMS. Still need to have it look ad total ADC and have a GUI to look at 1 channel, and not 2D.
June 6-10
Fixed the trigger signal. Set up data lines from GEMs. Fixed Hold/Clear/Clock signals.
June