Back to [[DVCS]]
+
Back to [[GMp]]
  
Previous tables
 
  
[[Task assignement August 15th 2010]]
+
Pending issues
 +
*HRS
 +
** FPP and DVCS electronics space ( Jack )
 +
** Is Right and Left HRS coincidence needed ? ( GMp collaboration , Doug )
 +
*Stand
 +
** interference sieve box, DVCS stand ( Gavalya, DVCS collaboration )
 +
*Target
 +
** Length of racetrack cell ( Bogdan )
 +
 
  
 
Experiment tasks
 
Experiment tasks
Line 10: Line 17:
 
*HV
 
*HV
 
*HRS calibration
 
*HRS calibration
*Beamline cablibration
+
*Beamline calibration
 
*dead time
 
*dead time
 
*lumi
 
*lumi
 
  
  
Line 26: Line 32:
 
|-
 
|-
 
|Alexandre Camsonne
 
|Alexandre Camsonne
| ARS DAQ, Slow control, decoding, paperwork
+
| HRS DAQ, DVCS DAQ, Compton
 
| Trigger
 
| Trigger
 
|  
 
|  
   * ARS test readout
+
   * <s>strike when done </s>
   * ARS final readout
+
   * Cosmics trigger
 +
  * 1877S install implement sparcification
 
   * Buffering test
 
   * Buffering test
   * DVCS HRS Trigger implementation
+
   * S0 GC trigger left arm
   * Test decoder
+
   * Efficiency trigger left arm
   * <s> Slow control LED </s>
+
   * S0 GC trigger right arm
   * Slow control current ADC
+
   * Efficiency trigger right arm
   * HRS integration
+
   *  
   * <s>COO</s>
+
   *  
  * <s>ESAD</s>
+
  * <s>RSAD</s>
+
  * TOSP
+
 
|
 
|
   * 100 % ( need implement checks and not working 100 % )
+
   * 0 %  
   * 60 % ( crates being added )
+
   * 0 %  
   * 90 % ( seems to work - need synch check )
+
   * 0 %  
   * 60% (  )
+
   * 0%  
   * 70 % ( need implement checks - several ROCs)
+
   * 0 %  
   * 100 % ( hardware ok - need write C functions driver and ROOT interface )
+
   * 0 %  
   * 95 % ( Full test with calo )
+
   * 0 %  
   * 80% ( waiting for crates to be in HRS )
+
   * 0%  
   * 90 % ( need edit files )
+
   * 0 %  
   * 30 % ( need adapt to DVCS )
+
   * 0 %  
   * 100 % ( Pavel waiting to send for signatures )
+
   * 0 %  
   * 0 % ( still not found old one )
+
   * 0 %  
 
|
 
|
   * NA
+
   *  
   * Aug 30 th
+
   *  
   * in progress 08/25/2010
+
   *  
   * 08/30/2010
+
   *  
   * 08/30/2010
+
   *  
   * 08/25/2010 ( 1 day )
+
   *  
   * 08/30/2010 ( cabling needed )
+
   *  
   * when everything in HRS, no later than september
+
   *  
   * 08/25/2010
+
   *  
   * 08/30/2010
+
   *  
   * 09/5/2010
+
   *  
   * 09/01/2010
+
   *
  | Setup DVCS crates in HRS
+
  |
 
|-
 
|-
 +
|Ole Hansen
 +
| Software, Tracking
 
|
 
|
| Lumi
 
 
|
 
|
 
|
 
|
 +
|
 +
|-
 +
|Dave Meekins
 +
| Target
 
|
 
|
 
|
 
|
| Lumi
+
|
 +
|
 +
|-
 +
|Doug
 +
| Beamline
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| Eric Christy
 +
|Run Plan
 +
*
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
|Al Gavalya
 +
| Design
 +
|
 +
|
 +
  *Resolve interference stand
 +
  *Final bid price scattering chamber
 +
|
 +
|
 +
|-
 +
| Robert Michaels
 +
| Trigger, Beamline
 +
| DAQ
 +
|
 +
*Helicity
 +
 
 +
|
 +
 
 +
|
 +
|
 +
 
 
}
 
}

Latest revision as of 23:32, 5 February 2016

Back to GMp


Pending issues

  • HRS
    • FPP and DVCS electronics space ( Jack )
    • Is Right and Left HRS coincidence needed ? ( GMp collaboration , Doug )
  • Stand
    • interference sieve box, DVCS stand ( Gavalya, DVCS collaboration )
  • Target
    • Length of racetrack cell ( Bogdan )


Experiment tasks

  • scalers
  • sync check
  • HV
  • HRS calibration
  • Beamline calibration
  • dead time
  • lumi


Name Expertise Secondary expert Task list Completion level / Completed / Left to be done Estimated completion date Main task
Alexandre Camsonne HRS DAQ, DVCS DAQ, Compton Trigger
 * strike when done 
 * Cosmics trigger
 * 1877S install implement sparcification
 * Buffering test
 * S0 GC trigger left arm
 * Efficiency trigger left arm
 * S0 GC trigger right arm
 * Efficiency trigger right arm
 * 
 * 

 * 0 % 
 * 0 % 
 * 0 % 
 * 0% 
 * 0 % 
 * 0 % 
 * 0 % 
 * 0% 
 * 0 % 
 * 0 % 
 * 0 % 
 * 0 % 
 * 
 * 
 * 
 * 
 * 
 * 
 * 
 * 
 * 
 * 
 * 
 *  
Ole Hansen Software, Tracking
Dave Meekins Target
Doug Beamline
Eric Christy Run Plan
Al Gavalya Design
 *Resolve interference stand
 *Final bid price scattering chamber
Robert Michaels Trigger, Beamline DAQ
  • Helicity

}