Difference between revisions of "Thursday, November 20: OWL Shift"
From Hall A Wiki
m |
|||
(3 intermediate revisions by the same user not shown) | |||
Line 9: | Line 9: | ||
** The target operator is required to supervise the cryo-target. | ** The target operator is required to supervise the cryo-target. | ||
** Kinematics, DVCS Kin1: Ebeam = 7.3 GeV, P<sub>LHRS</sub>=2.71 GeV, Theta_HRS=22.83, Theta_calo=12.35 | ** Kinematics, DVCS Kin1: Ebeam = 7.3 GeV, P<sub>LHRS</sub>=2.71 GeV, Theta_HRS=22.83, Theta_calo=12.35 | ||
− | ** Make sure to use the DVCS configuration for all runs. | + | ** <b>Note the controls for the left dipole are not stable, so do not change the momentum settings.</b> |
+ | ** Make sure to use the <b>DVCS CODA configuration</b> for all runs (<b>even when taking single arm HRS data</b>). | ||
** MCC should be finishing up beam studies near the beginning of Owl shift with hopefully stable CW beam operations to Halls A and D. | ** MCC should be finishing up beam studies near the beginning of Owl shift with hopefully stable CW beam operations to Halls A and D. | ||
+ | ** After completion of the beam tuning for Hall A, execute the following steps of the "Beamline" run plan [https://hallaweb.jlab.org/wiki/index.php/Beamline here]. For this part of the plan - contact Carlos (contact info on the white board). | ||
+ | *** Note that we will NOT be going through the Compton chicane. | ||
+ | *** Initial BPM/Raster checks/Beam centering | ||
+ | *** BPM Calibrations (Bullseye Scan) [1-2 hours] | ||
+ | *** Superharp Scan with Raster off/on | ||
+ | ** If time remains, start spectrometer checkout and begin looking for HRS-calorimeter coincidences. For this part of the plan - contact Carlos and Paul (contact info on the white board). The calorimeter HV will need to be turned on and put in the correct position - this will be done by Carlos or his assigned substitute. | ||
+ | ** Preliminary BCM Calibrations up to 10-20 μA, or what MCC can deliver if lower than this. |
Latest revision as of 21:51, 19 November 2014
Go back to Daily Run Plan Daily Run Plans
- General considerations
- Vincent Sulkosky is the current Run Coordinator. Please contact me directly via RC phone 757-876-1787
- Follow the generic Instructions for shift takers
- Shift leaders: Please make sure to fill out the beam time accounting form and write a "Shift Summary" log entry at the end of your shift regardless if there is beam or not.
- In general, technical staff should not be contacted by the shift crew - please call the RC first.
- Instructions for this shift
- The target operator is required to supervise the cryo-target.
- Kinematics, DVCS Kin1: Ebeam = 7.3 GeV, PLHRS=2.71 GeV, Theta_HRS=22.83, Theta_calo=12.35
- Note the controls for the left dipole are not stable, so do not change the momentum settings.
- Make sure to use the DVCS CODA configuration for all runs (even when taking single arm HRS data).
- MCC should be finishing up beam studies near the beginning of Owl shift with hopefully stable CW beam operations to Halls A and D.
- After completion of the beam tuning for Hall A, execute the following steps of the "Beamline" run plan here. For this part of the plan - contact Carlos (contact info on the white board).
- Note that we will NOT be going through the Compton chicane.
- Initial BPM/Raster checks/Beam centering
- BPM Calibrations (Bullseye Scan) [1-2 hours]
- Superharp Scan with Raster off/on
- If time remains, start spectrometer checkout and begin looking for HRS-calorimeter coincidences. For this part of the plan - contact Carlos and Paul (contact info on the white board). The calorimeter HV will need to be turned on and put in the correct position - this will be done by Carlos or his assigned substitute.
- Preliminary BCM Calibrations up to 10-20 μA, or what MCC can deliver if lower than this.