Difference between revisions of "SoLID Weekly : Monday, May.13, 2019 9:30am EDT"
From Hall A Wiki
(→Minutes) |
(Link to new wiki) |
||
(5 intermediate revisions by one other user not shown) | |||
Line 1: | Line 1: | ||
+ | This page has been moved to [https://solid.jlab.org/wiki/index.php/Weekly_:_Monday,_May.13,_2019_9:30am_EDT https://solid.jlab.org/wiki/index.php/Weekly_:_Monday,_May.13,_2019_9:30am_EDT] in the new [https://solid.jlab.org/wiki SoLID Wiki]. Please do not edit this page. | ||
+ | |||
== Agenda == | == Agenda == | ||
* Discussion on SoLID cost estimation according to WBS (Work Breakdown | * Discussion on SoLID cost estimation according to WBS (Work Breakdown | ||
Line 12: | Line 14: | ||
JP: We are looking for August, but it is quite difficult based on the current information. It is probably early September. | JP: We are looking for August, but it is quite difficult based on the current information. It is probably early September. | ||
*Nilanga: We should add the overhead, isn't? | *Nilanga: We should add the overhead, isn't? | ||
− | *JP: You just need to add your numbers. Jlab will use the average cost which includes everything you need. | + | *JP: You just need to add your numbers. And Jlab will use the average cost which includes everything you need. |
− | * | + | *Zhiwen: For the graduate student, should we count as 0.5 labor? |
+ | *JP: It is better to have the individual labor estimation. | ||
+ | *Zhiwen: From JP's table, it shows some detectors have the tracking cost, and some don't. | ||
+ | *JP: Shows an example on how to fill the table. If you don't include all the things that you needed in there, then you can't add more items later.After the meeting, I will send the form and the example. I will talk to you individually through this week(Wednesday to Friday).And I hope we will have the first round draft by Monday. | ||
+ | *JP: Seamus, I need to talk to you about the baffle estimation. | ||
+ | *Nilanga: Chips update. | ||
==Present== | ==Present== | ||
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen | Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen |
Latest revision as of 15:39, 7 December 2020
This page has been moved to https://solid.jlab.org/wiki/index.php/Weekly_:_Monday,_May.13,_2019_9:30am_EDT in the new SoLID Wiki. Please do not edit this page.
Agenda
- Discussion on SoLID cost estimation according to WBS (Work Breakdown
Structure)
- Sub-system updates
Minutes
- JP: Based on the Moller review feedback, we need to prepared more detail cost estimation. JP shows a table for the subsystem cost estimation, and he will send out this form to the person in charge of the subsystems.
- Paul: Things is changing by the time, so how do we handle the costing changing?
- JP: small change is normal, if it is a large change we need to discuss with the committee.
- Nilanga: Is the review is scheduled?
JP: We are looking for August, but it is quite difficult based on the current information. It is probably early September.
- Nilanga: We should add the overhead, isn't?
- JP: You just need to add your numbers. And Jlab will use the average cost which includes everything you need.
- Zhiwen: For the graduate student, should we count as 0.5 labor?
- JP: It is better to have the individual labor estimation.
- Zhiwen: From JP's table, it shows some detectors have the tracking cost, and some don't.
- JP: Shows an example on how to fill the table. If you don't include all the things that you needed in there, then you can't add more items later.After the meeting, I will send the form and the example. I will talk to you individually through this week(Wednesday to Friday).And I hope we will have the first round draft by Monday.
- JP: Seamus, I need to talk to you about the baffle estimation.
- Nilanga: Chips update.
Present
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen