Difference between revisions of "SoLID Weekly : Monday, May.13, 2019 9:30am EDT"

From Hall A Wiki
Jump to: navigation, search
(Minutes)
(Link to new wiki)
 
(3 intermediate revisions by one other user not shown)
Line 1: Line 1:
 +
This page has been moved to [https://solid.jlab.org/wiki/index.php/Weekly_:_Monday,_May.13,_2019_9:30am_EDT https://solid.jlab.org/wiki/index.php/Weekly_:_Monday,_May.13,_2019_9:30am_EDT] in the new [https://solid.jlab.org/wiki SoLID Wiki].  Please do not edit this page.
 +
 
== Agenda ==
 
== Agenda ==
 
* Discussion on SoLID cost estimation according to WBS (Work Breakdown
 
* Discussion on SoLID cost estimation according to WBS (Work Breakdown
Line 16: Line 18:
 
*JP: It is better to have the individual labor estimation.  
 
*JP: It is better to have the individual labor estimation.  
 
*Zhiwen: From JP's table, it shows some detectors have the tracking cost, and some don't.  
 
*Zhiwen: From JP's table, it shows some detectors have the tracking cost, and some don't.  
*JP: Shows a example on how to fill the table. If you don't include all the things that you needed in there, then you can't add more items later.
+
*JP: Shows an example on how to fill the table. If you don't include all the things that you needed in there, then you can't add more items later.After the meeting,  I will send the form and  the example.  I will talk to you individually through this week(Wednesday to Friday).And I hope we will have the first round draft by Monday.
 +
*JP: Seamus, I need to talk to you about the baffle estimation.
 +
*Nilanga: Chips update.
  
 
==Present==
 
==Present==
 
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen
 
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen

Latest revision as of 15:39, 7 December 2020

This page has been moved to https://solid.jlab.org/wiki/index.php/Weekly_:_Monday,_May.13,_2019_9:30am_EDT in the new SoLID Wiki. Please do not edit this page.

Agenda

  • Discussion on SoLID cost estimation according to WBS (Work Breakdown

Structure)

  • Sub-system updates

Minutes

  • JP: Based on the Moller review feedback, we need to prepared more detail cost estimation. JP shows a table for the subsystem cost estimation, and he will send out this form to the person in charge of the subsystems.
  • Paul: Things is changing by the time, so how do we handle the costing changing?
  • JP: small change is normal, if it is a large change we need to discuss with the committee.
  • Nilanga: Is the review is scheduled?

JP: We are looking for August, but it is quite difficult based on the current information. It is probably early September.

  • Nilanga: We should add the overhead, isn't?
  • JP: You just need to add your numbers. And Jlab will use the average cost which includes everything you need.
  • Zhiwen: For the graduate student, should we count as 0.5 labor?
  • JP: It is better to have the individual labor estimation.
  • Zhiwen: From JP's table, it shows some detectors have the tracking cost, and some don't.
  • JP: Shows an example on how to fill the table. If you don't include all the things that you needed in there, then you can't add more items later.After the meeting, I will send the form and the example. I will talk to you individually through this week(Wednesday to Friday).And I hope we will have the first round draft by Monday.
  • JP: Seamus, I need to talk to you about the baffle estimation.
  • Nilanga: Chips update.

Present

Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen