Difference between revisions of "Target Field and Kepco Power Supplies"

From Hall A Wiki
Jump to: navigation, search
(Plan for returning from CODIV shutdown)
 
(One intermediate revision by the same user not shown)
Line 19: Line 19:
  
 
==Field Measurements==
 
==Field Measurements==
 +
 +
==Plan for returning from CODIV shutdown==
 +
** Follow manufactureres "Check out" procedure for new power supply which was delivered during shutdown
 +
** Measure resistance to ground for both coils
 +
** Install latest new power supply, add additional circuitry
 +
** Test power supplies in both current and voltage control mode
 +
** Look at PS output on scope, with and without RF on.
 +
** Test NMR in both voltage and current mode
 +
** Ensure Labview is ready to go for either configuration

Latest revision as of 09:34, 1 June 2020

This page is dedicated to all things Target Field related

Log Entries

Coil Currents for D2n

Labview Program Guide

Field Measurements

Plan for returning from CODIV shutdown

    • Follow manufactureres "Check out" procedure for new power supply which was delivered during shutdown
    • Measure resistance to ground for both coils
    • Install latest new power supply, add additional circuitry
    • Test power supplies in both current and voltage control mode
    • Look at PS output on scope, with and without RF on.
    • Test NMR in both voltage and current mode
    • Ensure Labview is ready to go for either configuration