== Dec 22, Monday, 2008 ==
 
== Dec 22, Monday, 2008 ==
  
# Polarization calibration: EPR, NMR, Temperature
+
# AFP loss test of vertical pumping (HRS on)
# Polarization loss test
+
# EPR of vertical pumping (HRS on)
# HRS Magnet effect test: requires turning ON/OFF magnets for a couple of times
+
# NMR of vertical pumipng (HRS on)
# Check laser spectrum with cell
+
# Vertical temperature test @ pickup coil position (HRS on)
 +
# lunch and pumping
 +
# Vertical HRS test
 +
# Longitudinal HRS test
 +
# Chiranjib's temperature test
 +
# Check laser spectrum with cell ?
 
# Cool down oven
 
# Cool down oven
  
 
== Dec 23, Tuesday, 2008 ==
 
== Dec 23, Tuesday, 2008 ==
  
# RadCon surveys the target enclosure
+
# 09:30am: RadCon surveys the target enclosure
 
# remove the 3He cell and target ladder
 
# remove the 3He cell and target ladder
 
# Install water cell
 
# Install water cell
Line 34: Line 39:
  
 
=== Survey with the old needle horizontal compass ===
 
=== Survey with the old needle horizontal compass ===
# Keeping '''Transverse-''' field Put the old needle horizontal compass at the center point (~ 5min)
+
# Keeping '''Transverse-''' field, put the old needle horizontal compass at the center point (~ 5min)
 
# Survey the fourth point: Transverse-
 
# Survey the fourth point: Transverse-
 
# Change the field to '''Transverse+''' (~ 5min)
 
# Change the field to '''Transverse+''' (~ 5min)
 
# Survey the fifth point: Transverse+
 
# Survey the fifth point: Transverse+
# Change the field to '''Transverse+''' (~ 5min)
+
# Change the field to '''Longitudinal+''' (~ 5min)
 
# Survey the sixth point: Longitudinal+
 
# Survey the sixth point: Longitudinal+
# Change the field to '''Longitudinal+''' (~ 5min)
+
# Change the field to '''Longitudinal-''' (~ 5min)
 
# Survey the seventh point: Longitudinal-
 
# Survey the seventh point: Longitudinal-
  

Latest revision as of 12:44, 22 December 2008

Dec 22, Monday, 2008

  1. AFP loss test of vertical pumping (HRS on)
  2. EPR of vertical pumping (HRS on)
  3. NMR of vertical pumipng (HRS on)
  4. Vertical temperature test @ pickup coil position (HRS on)
  5. lunch and pumping
  6. Vertical HRS test
  7. Longitudinal HRS test
  8. Chiranjib's temperature test
  9. Check laser spectrum with cell ?
  10. Cool down oven

Dec 23, Tuesday, 2008

  1. 09:30am: RadCon surveys the target enclosure
  2. remove the 3He cell and target ladder
  3. Install water cell
  4. Prepare for water calibration: require turning off pump, other environment noise.
  5. Water calibration

Dec 24, Wednesday, 2008

  1. Water calibration

Dec 25, Thursday, 2008 - Jan 4, Sunday, 2009

  1. Compass measurement: Transverse, Vertical (optional)

Jan 5, Monday, 2009

Survey with the new horizontal compass

  1. With Transverse- field, put the new Horizontal Compass at Center point and align the laser before Survey starts
  2. Survey the first point: Transverse- Center
  3. Move compass to Upstream, align the laser (~ 30min)
  4. Survey the second point: Transverse- Upstream
  5. Move compass to Downstream, align the laser (~ 30min)
  6. Survey the third point: Transverse- Downstream

Survey with the old needle horizontal compass

  1. Keeping Transverse- field, put the old needle horizontal compass at the center point (~ 5min)
  2. Survey the fourth point: Transverse-
  3. Change the field to Transverse+ (~ 5min)
  4. Survey the fifth point: Transverse+
  5. Change the field to Longitudinal+ (~ 5min)
  6. Survey the sixth point: Longitudinal+
  7. Change the field to Longitudinal- (~ 5min)
  8. Survey the seventh point: Longitudinal-

After compass survey

  1. Install 3He cell and ladder

Jan 6, Tuesday, 2009

  1. Target Survey

Jan 7, Wednesday, 2009 - Beam start

  1. Laser check
  2. Pumping
  3. Polarization calibration