Difference between revisions of "Meeting 2022 04 27"
From Hall A Wiki
(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
(→Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)) |
||
(3 intermediate revisions by 2 users not shown) | |||
Line 14: | Line 14: | ||
=== Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) === | === Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo) === | ||
− | * | + | * Parts are coming in for installing into SBS EEL setup. |
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) === | === Update on UVa GEM layers for GEn-RP (Anu, John, Thir) === | ||
Line 20: | Line 20: | ||
=== Update on BB GEMs(Sean, Ezekiel, Holly, Anu) === | === Update on BB GEMs(Sean, Ezekiel, Holly, Anu) === | ||
− | * | + | * UV layers 3 and 4 (counting 1 - 4) had dividers replaced with new 2-path divider boards |
+ | * Both had HV tests and everything went as expected. | ||
+ | * APVs with missing strips were replaced on both layers. | ||
+ | * All layers are now installed back into BB and we are waiting for parts to take out layer 1 and install the parallel HV supply. | ||
=== DAQ updates (Ben, Bryan, Alex) === | === DAQ updates (Ben, Bryan, Alex) === |
Latest revision as of 10:27, 27 April 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan (all)
- Installation of HV dividers on BB: work plan
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
Update on INFN GEM layers for GEn-RP (Ezekiel, Holly, Evaristo)
- Parts are coming in for installing into SBS EEL setup.
Update on UVa GEM layers for GEn-RP (Anu, John, Thir)
Update on BB GEMs(Sean, Ezekiel, Holly, Anu)
- UV layers 3 and 4 (counting 1 - 4) had dividers replaced with new 2-path divider boards
- Both had HV tests and everything went as expected.
- APVs with missing strips were replaced on both layers.
- All layers are now installed back into BB and we are waiting for parts to take out layer 1 and install the parallel HV supply.
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A