(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
(→Update on BB GEMs) |
||
(One intermediate revision by one other user not shown) | |||
Line 10: | Line 10: | ||
=== Update on BB GEMs === | === Update on BB GEMs === | ||
− | * Layer 0 current draw | + | * Layer 0 current draw - keep live plot up when changing the voltages! |
+ | * CM plots have looked unusual and is being investigated | ||
+ | ** This is likely due to some offline analysis issues, all the data taking should still be working fine. | ||
=== Update on layers for GEn-RP === | === Update on layers for GEn-RP === |
Latest revision as of 10:26, 2 November 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Commissioning of the GEMs:
- See: [1]
Update on BB GEMs
- Layer 0 current draw - keep live plot up when changing the voltages!
- CM plots have looked unusual and is being investigated
- This is likely due to some offline analysis issues, all the data taking should still be working fine.
Update on layers for GEn-RP
- Stand alone DAQ:
- need to resolve INFN LV
- need to keep running and monitor crashes
- need radiation measurement
- SBS premix gas delivery today
DAQ updates (Ben, Bryan, Alex)
- File to evio insertion error?