== Work delayed by LOTO pause ==
 +
* SBS power supply troubleshooting (Friday, May 24)
 +
* SHMS cooldown (Tuesday, May 28)
 +
* Hall A Compton laser work (Wednesday, May 29)
 +
* Hall C: NPS magnet removal
 +
* Hall A: BigBite removal
 +
* Compton photon table work
 +
 +
== Admin locks applied for longer than 1 week (please list below) ==
 +
* ??
 +
 +
== ePAS permits ==
 +
* ePAS info in the EH&S manual: https://www.jlab.org/ehs/ehsmanual/ePAS__manual%20section%202_rev0.htm
 +
* Hall C Moller - operation and measurement: JLab-PTW-1307
 +
* Compton laser lab: JLab-PTW-1098
 +
* Hall A Compton: JLab-PTW-1359
 +
* NPS power supply LOCAL operation: JLab-PTW-1617
 +
* NPS correctors - LOCAL operation: JLab-PTW-1638
 +
* HMS Quads: JLAB-PTW-1699
 +
* HMS Dipole: JLAB-PTW-1701
 +
* SBS power supply LOCAL operation: JLAB-PTW-1703
 +
* SBS corrector LOCAL operation JLAB-PTW-1722
 +
* Power supply repair and maintenance (Ellen)
 +
* Hall C Spectrometer rotation reset JLAB-PTW-1723
 +
* Hall C Spectrometer rotation (remote or local) JLAB-PTW-1605-rev1
 +
* Grinch (Big Bite): JLAb-PTW-2148
 +
* Cryo Heidi JLAB-PR-1203
 +
* Spectrometer gas systems (Chandan, Bill)
 +
* Tabletop electronic troubleshooting (Mode 1 and 2) JLAB-PTW-????
 +
 +
== Hall A Work for GEP (next SAD) ==
 +
* Moller dipole power supply
 +
* Power for ECAL racks - 10 NIM crates, up to 300 W each
 +
* Transformer for ECAL heater power. Need 480 VAC, 200A supply
 +
* More GEM low voltage - BB GEMS are moving to SBS
 +
* Interlock switches for ECAL panels (Ellen)
 +
* Moller magnet vacuum (Ellen)
 +
* Compton laser mirror replacement (Dave w/help from Lars)
 +
* Compton photon detector table repair (Sam)
 +
* Compton laser polarization measurement (Sam)
 +
* Big Bite related tasks (won't be used)
 +
* Pull all Hall A left arm U-tubes, install jumper to N2 return. (heidi-Paperwork in progress)
 +
* Decommission left arm supplies (Heidi-work request submitted)
 +
* MOLLER prep: relocate 480 junction box, identify cables above beamline
 +
* Add jmenu controls for GEM LV? Is browser interface sufficient?
 +
* figure out white junction box above beamline for Moller (Joe)
 +
* SBS regulation (Joe)
 +
* ECAL connector soldering (Lars)
 +
* GEM gas line repair (Lars), COMPLETE
 +
* Add rails to rack (Lars), COMPLETE
 +
* Nitrogen dewar for GEMS (Lars)
 +
 +
== Hall C Work for LAD ==
 +
* Power for GEM racks (Joe?)
 +
* NPS calorimeter and sweeper removal
 +
* All the things for getting SHMS working again - bender will be reinstalled (all).  See Cryo "SAD" list below
 +
* Figure out SHMS encoder drift
 +
* hall C moller compressor comms and filter
 +
* remove NDX detectors from hall C (in progress)
 +
* Guards on HMS dipole leads-(Lars)
 +
* HMS drift chamber low voltage supply replacements
 +
* HMS Shield door motor drive replacement
 +
* Rotation shunt-trip breakers: replace or buy spares (Steve L. suggestion)
 +
* Get circuit breaker reset stick (Steve L. suggestion)
 +
* Label and track NPS equipment (Lars)
 +
* Find Andy's files (?)
 +
 
== Priority Items ==
 
== Priority Items ==
 +
* Check your own PPE
 +
* Have Dave G check your PPE
 +
* Locate Jack's property (all)
 +
* Moller maintenance ePAS
 +
* Sieve slit controllers ePAS
 +
* BigBite Argon manifold pressure sensor erratic. Need to clean the connections
 +
* SBS Argon pressure sensor bad?
 +
* Work with Brad and Steve Lassiter to get Skylla10 moved from physical hardware to virtual machine (Ellen)
 +
* Version control software for Hall C PLC code (Ellen)
  
SE-II search
+
== Cryo ==
  
Check HMS NMR connection
 
  
HMS drift chamber low voltage supply replacements
 
  
Moller maintenance OSP
+
Build local valve control boxes with local read out. (Heidi-in progress)
  
SBS corrector OSP?
+
op check/repair hall C vacuum gauges (in progress - Lars)
  
Sieve slit controllers OSP
+
Insulate HMS N2 4k shield (stinger) return line.(Lars)
  
VVUs on HMS
+
Repair calibrate JT valve spares. (Lars)
  
Guards on HMS dipole leads
+
Update code for the new temperature sensor installed on the HX N2 vent on the HMS. (Ellen?)
  
Oscillator for LN2 level meter
+
Check penning gauges on HMS Quads (software or hardware problem?) (Ellen/Lars)
  
BigBite Argon manifold pressure sensor erratic. Need to clean the connections?
+
PLC/Code changes (Heidi/Ellen-in progress)
  
Some of the SBS magnet bus bars have been running hot. Do we need to re-torque them?
+
Assemble L Tube/relief valve assembly (Lars)
  
Readout for LCW pressure sensors added at end of beamline walkway (not started)
+
U-Tube ePass/fall protection, Hall A (Heidi) -Paperwork submitted
  
== Cryo ==
+
Remove all hal A left arm U-tubes
  
Pump-out (CVI) replacement (Lars)
 
  
Remove actuators from right arm magnets (Hall A). (Dipole/Q3 complete)
 
  
Build local valve control boxes with local read out.
 
  
op check/repair hall C vacuum gauges (in progress - Lars)
 
  
Troubleshoot HMS Q1 LN2 temp sensors.
+
'''SAD'''
  
Check HMS Quad magnet leads for leaks/repair.
+
Warm HMS Dipole to 90K and pump
  
Troubleshoot HMS Dipole LN2 siphon temp.
+
Troubleshoot/repair HMS DI He in and He 3 temp sensors -Done
  
Extend HMS Q1 warm return control wires and re-terminate/calibrate.
+
Troubleshoot HMS Q1 LN2 temp sensors. (Heidi-SAD)
  
Check all JT actuators, ensure belt is functional and in the correct orientation.
+
Check HMS Quad magnet leads for leaks/repair. (Heidi-SAD)
  
Insulate HMS N2 4k shield (stinger) return line.
+
Troubleshoot HMS Dipole LN2 siphon temp. (Heidi-SAD)
  
Insulate SHMS Warm return line across pivot.
+
Troubleshoot HMS Q1  PT-17/PT-18 temp sensors. (Heidi-SAD)
  
Repair calibrate warm return valve spares.
+
Install environmental splices SHMS Dipole liquid level line (Heidi-SAD)
  
Repair calibrate JT valve spares.
+
Cool SHMS Dipole, Q3, Q2, Q1. (Heidi)
  
Troubleshoot HMS Quad Vac gauges.  
+
After HB magnet electronics controls installation complete, cool HB Magnet. (Heidi)
  
Move the SHMS lead flow controllers and coordinate with the Cryo group (need engineering support).
+
Repair lead leak on HMS Dipole leads.(Heidi/Lars)
  
SHMS Lead flow, - add upstream valves to isolate each lead flow, for easier replacement of valve/flow meter. (install when meters are moved to new location)
+
Cool HMS Dipole.(Heidi)
  
Update code for the new temperature sensor installed on the HX N2 vent on the HMS.  
+
Insulate stinger N2 return line (Lars)
 +
 
 +
Add "T's" and pump out ports to HMS magnet vacuum gauge ports. (Lars)
  
 
Move temps from Honeywell to PLC controls. (if channels are available)  
 
Move temps from Honeywell to PLC controls. (if channels are available)  
  
Add "T's" and pump out ports to HMS magnet vacuum gauge ports.
+
Extend HMS Q1 warm return control wires and re-terminate/calibrate. (Heidi-pigtail made/SAD)
  
 +
Remove actuators from right and left arm magnets (Hall A). (Dipole/Q3 complete) (Heidi, Lars)
  
 +
Pump-out (CVI) replacement (Larry)-on hold
  
 +
Install new lead flow controller HMS Dipole (Heidi)
  
  
Warm up SHMS Dipole.
+
'''''Not This SAD'''''
  
De-sting SHMS 4k He supply transfer line.
+
De-sting SHMS 4k He supply transfer line. (Heidi)-
 +
De-sting SHMS DI 4k He supply line. (Heidi)?
  
Repair SHMS 4k supply transfer line ball valve assembly.
+
Repair SHMS 4k supply transfer line ball valve assembly. (Heidi/Lars)
 +
Install new PHPK vac valve (techs)
  
Re-sting SHMS 4k transfer line.
+
Re-sting SHMS 4k transfer line/DI 4k supply. (Heidi)
  
Cool SHMS Dipole, Q3, Q2, Q1.
+
Move the SHMS lead flow controllers and coordinate with the Cryo group (need engineering support).
  
After HB magnet electronics controls installation complete, cool HB Magnet.
+
SHMS Lead flow, - add upstream valves to isolate each lead flow, for easier replacement of valve/flow meter. (install when meters are moved to new location-need engineering /design support)
  
Warm HMS Dipole (to 300k for lead repair)
+
== Electrical ==
  
Repair lead leak on HMS Dipole leads.
+
Isolating power switches on HMS power supplies, maybe
  
Cool HMS Dipole.
+
Specifications for power supplies for HKS (coordinate with Onish)
  
== Electrical ==
+
Get Unser repaired --> not possible. Dave Mack took to Fast Electronics
  
Capacitor discharge stick
+
capacitor bank VVUs for hall A magnets (Ellen/Sam)
  
Isolating power switches on HMS power supplies
+
check/label HMS quad pivot cabinet with proper electrical labels if needed
  
Specifications for power supplies for HKS (coordinate with Sarin)
+
== Spectrometers ==
  
Get Unser repaired
+
Make HMS dipole NMR lock better, replace gain pot with spare?
  
Hall A Compton photon detector table motion (somebody cut the cables)
+
Finish refurbishing NMR multiplexer for hall C
  
GEM low voltage distribution
+
Rotation software improvement for hall C
  
== Spectrometers ==
+
skylla10 migration
  
Make HMS dipole NMR lock better
+
hms quad vacuum gauges not working
  
 
Hall probes/NMR (?) for HKS
 
Hall probes/NMR (?) for HKS
 +
 +
Add 2nd raspberry pi for HMS prescale
  
 
== Gas systems ==
 
== Gas systems ==
Line 112: Line 191:
  
 
== Possible Future Items ==
 
== Possible Future Items ==
 +
 +
Reboot switch for I2C devices

Latest revision as of 08:22, 15 July 2024

Work delayed by LOTO pause

  • SBS power supply troubleshooting (Friday, May 24)
  • SHMS cooldown (Tuesday, May 28)
  • Hall A Compton laser work (Wednesday, May 29)
  • Hall C: NPS magnet removal
  • Hall A: BigBite removal
  • Compton photon table work

Admin locks applied for longer than 1 week (please list below)

  •  ??

ePAS permits

  • ePAS info in the EH&S manual: https://www.jlab.org/ehs/ehsmanual/ePAS__manual%20section%202_rev0.htm
  • Hall C Moller - operation and measurement: JLab-PTW-1307
  • Compton laser lab: JLab-PTW-1098
  • Hall A Compton: JLab-PTW-1359
  • NPS power supply LOCAL operation: JLab-PTW-1617
  • NPS correctors - LOCAL operation: JLab-PTW-1638
  • HMS Quads: JLAB-PTW-1699
  • HMS Dipole: JLAB-PTW-1701
  • SBS power supply LOCAL operation: JLAB-PTW-1703
  • SBS corrector LOCAL operation JLAB-PTW-1722
  • Power supply repair and maintenance (Ellen)
  • Hall C Spectrometer rotation reset JLAB-PTW-1723
  • Hall C Spectrometer rotation (remote or local) JLAB-PTW-1605-rev1
  • Grinch (Big Bite): JLAb-PTW-2148
  • Cryo Heidi JLAB-PR-1203
  • Spectrometer gas systems (Chandan, Bill)
  • Tabletop electronic troubleshooting (Mode 1 and 2) JLAB-PTW-????

Hall A Work for GEP (next SAD)

  • Moller dipole power supply
  • Power for ECAL racks - 10 NIM crates, up to 300 W each
  • Transformer for ECAL heater power. Need 480 VAC, 200A supply
  • More GEM low voltage - BB GEMS are moving to SBS
  • Interlock switches for ECAL panels (Ellen)
  • Moller magnet vacuum (Ellen)
  • Compton laser mirror replacement (Dave w/help from Lars)
  • Compton photon detector table repair (Sam)
  • Compton laser polarization measurement (Sam)
  • Big Bite related tasks (won't be used)
  • Pull all Hall A left arm U-tubes, install jumper to N2 return. (heidi-Paperwork in progress)
  • Decommission left arm supplies (Heidi-work request submitted)
  • MOLLER prep: relocate 480 junction box, identify cables above beamline
  • Add jmenu controls for GEM LV? Is browser interface sufficient?
  • figure out white junction box above beamline for Moller (Joe)
  • SBS regulation (Joe)
  • ECAL connector soldering (Lars)
  • GEM gas line repair (Lars), COMPLETE
  • Add rails to rack (Lars), COMPLETE
  • Nitrogen dewar for GEMS (Lars)

Hall C Work for LAD

  • Power for GEM racks (Joe?)
  • NPS calorimeter and sweeper removal
  • All the things for getting SHMS working again - bender will be reinstalled (all). See Cryo "SAD" list below
  • Figure out SHMS encoder drift
  • hall C moller compressor comms and filter
  • remove NDX detectors from hall C (in progress)
  • Guards on HMS dipole leads-(Lars)
  • HMS drift chamber low voltage supply replacements
  • HMS Shield door motor drive replacement
  • Rotation shunt-trip breakers: replace or buy spares (Steve L. suggestion)
  • Get circuit breaker reset stick (Steve L. suggestion)
  • Label and track NPS equipment (Lars)
  • Find Andy's files (?)

Priority Items

  • Check your own PPE
  • Have Dave G check your PPE
  • Locate Jack's property (all)
  • Moller maintenance ePAS
  • Sieve slit controllers ePAS
  • BigBite Argon manifold pressure sensor erratic. Need to clean the connections
  • SBS Argon pressure sensor bad?
  • Work with Brad and Steve Lassiter to get Skylla10 moved from physical hardware to virtual machine (Ellen)
  • Version control software for Hall C PLC code (Ellen)

Cryo

Build local valve control boxes with local read out. (Heidi-in progress)

op check/repair hall C vacuum gauges (in progress - Lars)

Insulate HMS N2 4k shield (stinger) return line.(Lars)

Repair calibrate JT valve spares. (Lars)

Update code for the new temperature sensor installed on the HX N2 vent on the HMS. (Ellen?)

Check penning gauges on HMS Quads (software or hardware problem?) (Ellen/Lars)

PLC/Code changes (Heidi/Ellen-in progress)

Assemble L Tube/relief valve assembly (Lars)

U-Tube ePass/fall protection, Hall A (Heidi) -Paperwork submitted

Remove all hal A left arm U-tubes



SAD

Warm HMS Dipole to 90K and pump

Troubleshoot/repair HMS DI He in and He 3 temp sensors -Done

Troubleshoot HMS Q1 LN2 temp sensors. (Heidi-SAD)

Check HMS Quad magnet leads for leaks/repair. (Heidi-SAD)

Troubleshoot HMS Dipole LN2 siphon temp. (Heidi-SAD)

Troubleshoot HMS Q1 PT-17/PT-18 temp sensors. (Heidi-SAD)

Install environmental splices SHMS Dipole liquid level line (Heidi-SAD)

Cool SHMS Dipole, Q3, Q2, Q1. (Heidi)

After HB magnet electronics controls installation complete, cool HB Magnet. (Heidi)

Repair lead leak on HMS Dipole leads.(Heidi/Lars)

Cool HMS Dipole.(Heidi)

Insulate stinger N2 return line (Lars)

Add "T's" and pump out ports to HMS magnet vacuum gauge ports. (Lars)

Move temps from Honeywell to PLC controls. (if channels are available)

Extend HMS Q1 warm return control wires and re-terminate/calibrate. (Heidi-pigtail made/SAD)

Remove actuators from right and left arm magnets (Hall A). (Dipole/Q3 complete) (Heidi, Lars)

Pump-out (CVI) replacement (Larry)-on hold

Install new lead flow controller HMS Dipole (Heidi)


Not This SAD

De-sting SHMS 4k He supply transfer line. (Heidi)- De-sting SHMS DI 4k He supply line. (Heidi)?

Repair SHMS 4k supply transfer line ball valve assembly. (Heidi/Lars) Install new PHPK vac valve (techs)

Re-sting SHMS 4k transfer line/DI 4k supply. (Heidi)

Move the SHMS lead flow controllers and coordinate with the Cryo group (need engineering support).

SHMS Lead flow, - add upstream valves to isolate each lead flow, for easier replacement of valve/flow meter. (install when meters are moved to new location-need engineering /design support)

Electrical

Isolating power switches on HMS power supplies, maybe

Specifications for power supplies for HKS (coordinate with Onish)

Get Unser repaired --> not possible. Dave Mack took to Fast Electronics

capacitor bank VVUs for hall A magnets (Ellen/Sam)

check/label HMS quad pivot cabinet with proper electrical labels if needed

Spectrometers

Make HMS dipole NMR lock better, replace gain pot with spare?

Finish refurbishing NMR multiplexer for hall C

Rotation software improvement for hall C

skylla10 migration

hms quad vacuum gauges not working

Hall probes/NMR (?) for HKS

Add 2nd raspberry pi for HMS prescale

Gas systems

Do We Still Need To Do These?

Possible Future Items

Reboot switch for I2C devices