== Task I : Beamline Commissioning (Y. Roblin) == | == Task I : Beamline Commissioning (Y. Roblin) == | ||
− | Initial Beam Accelerator Ops, with assistance from the Hall A shift crew. This includes delivery of beam to the dump, commissioning of the BPMs, calibration with the Harp and power up of the rasters. | + | Initial Beam Accelerator Ops, with assistance from the Hall A shift crew. This includes delivery of beam to the dump, commissioning of the BPMs, calibration with the Harp and power up of the rasters. |
Full Details for ONLY straight-through beam delivery are provided at: | Full Details for ONLY straight-through beam delivery are provided at: | ||
Line 21: | Line 21: | ||
# Polarized Target: Field OFF | # Polarized Target: Field OFF | ||
− | <U> Beam Diagnostics Check-out</U> ( Pengjia, Alexandre, Kalyan) | + | <U> Beam Diagnostics Check-out</U> (Pengjia, Alexandre, Kalyan) |
# Check BPM, slow and fast raster signals in the data | # Check BPM, slow and fast raster signals in the data | ||
# Is spot++ working for both arms? | # Is spot++ working for both arms? | ||
Line 28: | Line 28: | ||
+ | == Tungsten Calorimeter Check-out == | ||
− | + | (Resp: Alexandre, Pengjia) | |
− | + | # Commission tungsten calorimeter | |
+ | # BCM calibration ? | ||
+ | # How do we establish that we can achieve ~1% measurement ? | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | == | + | == HRS/Detector Checkout == |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
(Resp: g2p students) | (Resp: g2p students) | ||
Line 92: | Line 83: | ||
# Measure lumi asymmetries | # Measure lumi asymmetries | ||
− | |||
− | + | == Optics Commissioning == | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | == | + | |
(Resp: Jixie, Min, Vince et al.). | (Resp: Jixie, Min, Vince et al.). | ||
Line 108: | Line 91: | ||
*[http://hallaweb.jlab.org/experiment/g2p/collaborators/jixie/20120226_Optics_Final/g2p_optics_plan.pdf Optics run plan] | *[http://hallaweb.jlab.org/experiment/g2p/collaborators/jixie/20120226_Optics_Final/g2p_optics_plan.pdf Optics run plan] | ||
− | == | + | == On-line Analysis == |
(Resp: Toby) | (Resp: Toby) | ||
Line 121: | Line 104: | ||
# Start-of-Run and End-of-Run information is up to date with all relevant info | # Start-of-Run and End-of-Run information is up to date with all relevant info | ||
− | |||
− | |||
− | + | == Compton Test (2 shifts) == | |
− | == | + | (Resp: Sirish et al.) |
+ | |||
+ | |||
+ | == Moller Commissioning (1 shift) == | ||
+ | |||
+ | (Resp: O. Glamazdin, J. Zhang) | ||
+ | |||
+ | # Detector HV tuning (30min) | ||
+ | # Q1 and Q2 quadruple magnets scan (1hour) | ||
+ | # Moller target longitudinal scan (30 min) | ||
+ | # Beam polarization measurement (30-40min) | ||
+ | # MCC job (to set Moller settings and to restore previous beam parameters) (~2hours) | ||
+ | Total: 5 hours. | ||
+ | |||
+ | |||
+ | == Polarized Target == | ||
(Resp : Target group ) | (Resp : Target group ) | ||
# ?? | # ?? | ||
+ | |||
+ | == Beam Energy Measurement == | ||
+ | |||
+ | (Resp: Vince?) | ||
+ | |||
+ | # Mott ? |
Revision as of 18:55, 27 February 2012
E08-027/E08-007 Commissioning Runplan (K. Slifer / K. Allada)
Contents
Task I : Beamline Commissioning (Y. Roblin)
Initial Beam Accelerator Ops, with assistance from the Hall A shift crew. This includes delivery of beam to the dump, commissioning of the BPMs, calibration with the Harp and power up of the rasters.
Full Details for ONLY straight-through beam delivery are provided at:
Start-up configuration
- Two pass beam, E0 =2.2 GeV, polarized, no raster.
- Current: Initially pulsed up to 2-4<math>\mu</math>A pulsed, then up to 5 <math>\mu</math>A CW.
- Spectrometers at 12.5 degrees, <math>P_0=??</math> MeV (carbon elastic).
- Sieve slits : OUT.
- Septa settings: 5.69 degrees.
- Compton chicane: OFF.
- Polarized Target chicane : OFF and degaussed.
- Tungsten Calorimeter : Retracted.
- Polarized Target: Field OFF
Beam Diagnostics Check-out (Pengjia, Alexandre, Kalyan)
- Check BPM, slow and fast raster signals in the data
- Is spot++ working for both arms?
- BPM commissioning plan by Pengjia here
- Check BCM signals in the scalers
Tungsten Calorimeter Check-out
(Resp: Alexandre, Pengjia)
- Commission tungsten calorimeter
- BCM calibration ?
- How do we establish that we can achieve ~1% measurement ?
HRS/Detector Checkout
(Resp: g2p students)
Most of these check-out can be done during the initial beamline commissioning(see above)
HRS Detectors Check-out (Melissa, Ryan, Vince)
- Check all the detectors in both arm to establish that we don't have problems.
- Post ALL the online plots for the detectors (ADC, TDC etc..) in the Halog
- VDC (efficiencies etc..)
- Gas Cerenkov (ADC and timing peaks)
- S1 and S2m (ADC and timing peaks)
- Lead-glass Calorimeter (ADC)
- Check HV on all the detectors, align the peaks if necessary
DAQ/Trigger Check-out (Melissa, Ryan, Vince)
- Establish the DAQ conditions for production
- What is the max rate DAQ can run with < 20% DT (Buffered and unbuffered mode) ?
- Record deadtime as a function of DAQ rate. Change rate via current or prescalers.
- Check synchronization of ROCs in buffered mode
- Make sure all important scaler channels are working (BCM, Helicity, triggers, L1A, clock)
- Check scalers in S1 and S2m detectors for double pulsing
HRS and Septum Magnet Checks (Min, Jixie?)
- Cycle magnets
- Septum field vs current, checks with carbon elastic peaks
Third Arm Detector Check-out (Chao, Kalyan)
- Set thresholds for 2.2 GeV beam
- Check for bad channels, double peaks etc ..
- Check deadtime, helicity, BCM scalers
Helicity Checks (Chao, Pengjia, Kalyan)
- Larger charge asymmetry runs to check BCM/helicity signals in HAPPEX, HRS, thirdarm, Moller DAQs simultaneously
- Establish that there are no problems by checking Hall-A beam charge asymmetries measured in Hall-C
Lumi Detector Check-out (Pengjia, Kalyan)
- Adjust HV with 100nA current to make sure all channels are roughly aligned and there is no saturation in Happex ADC
- Establish non linearity of the Lumi detectors
- Measure lumi asymmetries
Optics Commissioning
(Resp: Jixie, Min, Vince et al.).
Full details are provided at:
On-line Analysis
(Resp: Toby)
- Make sure all on-line analysis scripts are up to date on both arms
- Post easy instructions for the shift crew on how to start online analysis (stick notes near the DAQ machine)
- Make sure all the important information is recorded correctly in the datastream:
- EPICS: Beam diagnostics(BCM, BPM, HARP etc..)
- Target variables
- Helicity sorted scalers information ( triggers, L1A, BCM, helicity etc.)
- Helicity in ADC, scaler, TIR
- Start-of-Run and End-of-Run information is up to date with all relevant info
Compton Test (2 shifts)
(Resp: Sirish et al.)
Moller Commissioning (1 shift)
(Resp: O. Glamazdin, J. Zhang)
- Detector HV tuning (30min)
- Q1 and Q2 quadruple magnets scan (1hour)
- Moller target longitudinal scan (30 min)
- Beam polarization measurement (30-40min)
- MCC job (to set Moller settings and to restore previous beam parameters) (~2hours)
Total: 5 hours.
Polarized Target
(Resp : Target group )
- ??
Beam Energy Measurement
(Resp: Vince?)
- Mott ?