*Documentation for Reviewers
+
==Documentation for Reviewers==
**[http://hallaweb.jlab.org/12GeV/SuperBigBite/documents/report_of_DOE_review_panel_for_SBS_2013.pdf Final report] from DOE Nov 2013 SBS review.
+
===Response to DOE 2013 review report===
**DOE Nov 2013 recommendations with responses.
+
*[http://hallaweb.jlab.org/12GeV/SuperBigBite/documents/report_of_DOE_review_panel_for_SBS_2013.pdf Final report] from DOE Nov 2013 SBS review.
***Update the work flow for GEM module construction to include workforce (by type) required for each step.
+
*DOE Nov 2013 recommendations with responses.
****DOE SBS Nov 2013 monthly report included the work flow for GEM module construction to include workforce (by type).  
+
#''Update the work flow for GEM module construction to include workforce (by type) required for each step.''
****Need Evaristo and Nilanga to update.
+
#*DOE SBS Nov 2013 monthly report included the work flow for GEM module construction to include workforce (by type).  
***Develop a written Quality Assurance/test plan, including acceptance criteria for foils and assembled chambers that will be used for both UVa and INFN.  
+
#*<span style="color: red">Need Evaristo and Nilanga to update.</span>
****Need Evaristo and Nilanga to create.
+
#''Develop a written Quality Assurance/test plan, including acceptance criteria for foils and assembled chambers that will be used for both UVa and INFN.''
***Conduct a background assessment for each experimental program that includes background rejection and signal efficiency as a function of trigger cuts, and present at the next review.  
+
#*<span style="color: red"> Need Evaristo and Nilanga to create.</span>
****Seamus is leading the effort.
+
#''Conduct a background assessment for each experimental program that includes background rejection and signal efficiency as a function of trigger cuts, and present at the next review.''
***Develop a document describing the interface between the DAQ system and each of the 3 types of electronics (FADC, GEM, and FASTBUS) and present at the next review.
+
#*<span style="color: green"> Seamus is leading the effort.
****Alexandre is leading the effort.
+
#''Develop a document describing the interface between the DAQ system and each of the 3 types of electronics (FADC, GEM, and FASTBUS) and present at the next review.''
***Integration milestones for all equipment off-project, as well as key JLAB readiness and safety reviews, should be incorporated into the list of milestones. Provide updated list of milestones to DOE by January 1, 2014.
+
#*<span style="color: green"> Alexandre is leading the effort.
****List of milestones for off-project equipment dependencies was sent to DOE in Nov 2013 monthly report.  
+
#''Integration milestones for all equipment off-project, as well as key JLAB readiness and safety reviews, should be incorporated into the list of milestones. Provide updated list of milestones to DOE by January 1, 2014.''
***Develop a Technical Specifications Document for all experimental components in the SBS program and present it at the next annual review.
+
#*List of milestones for off-project equipment dependencies was sent to DOE in Nov 2013 monthly report.  
****Need from each set of equipment a list of technical specs.
+
#''Develop a Technical Specifications Document for all experimental components in the SBS program and present it at the next annual review.''
***Develop an integration plan for all experimental components (on and off project) needed for the SBS program, which includes activities, schedules and goals.
+
#*<span style="color: red"> Need from each set of equipment a list of technical specs.
****Need from each set of equipment a list of  activities, schedules and goals.
+
#''Develop an integration plan for all experimental components (on and off project) needed for the SBS program, which includes activities, schedules and goals.''
***Update the Research Management Plan to capture current plans for scientific effort needed to implement the project.
+
#*<span style="color: red"> Need from each set of equipment a list of  activities, schedules and goals.
****[http://hallaweb.jlab.org/12GeV/SuperBigBite/documents/RMP-2014.pdf Research Management Plan]. Updated and sent to DOE in Jan 2014 Monthly report.
+
#''Update the Research Management Plan to capture current plans for scientific effort needed to implement the project.''
****Need one-page activity report from each group to be sent to Brian Quinn
+
#*[http://hallaweb.jlab.org/12GeV/SuperBigBite/documents/RMP-2014.pdf Research Management Plan]. Updated and sent to DOE in Jan 2014 Monthly report.
***The Project Management Plan should be updated to reflect changes in scope to the WBS components and evolving list of off-project equipment.
+
#*<span style="color: red"> Need one-page activity report from each group to be sent to Brian Quinn
****[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/sbs_pmp-new-cd-mkj-4.pdf Program Management Plan]. Updated to include PMT based Coordinate Detector and list of off-project equipment dependencies and submitted to DOE in Jan 2014.  
+
#''The Project Management Plan should be updated to reflect changes in scope to the WBS components and evolving list of off-project equipment.''
**DOE SBS Monthly reports
+
#*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/sbs_pmp-new-cd-mkj-4.pdf Program Management Plan]. Updated to include PMT based Coordinate Detector and list of off-project equipment dependencies and submitted to DOE in Jan 2014.  
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2013dec15_v1.pdf Nov 2013], [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014jan15_v1.pdf Dec 2013],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/03/jlab_sbs_monthly-report_2014feb15-rmp.pdf Jan 2014], [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014mar15.pdf Feb 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014apr15.pdf Mar 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014may15.pdf Apr 2014]
+
===DOE SBS Monthly reports===
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014june15.pdf May 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014july15.pdf June 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/jlab_sbs_monthly-report_2014aug15-with_gemreport.pdf July 2014]
+
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2013dec15_v1.pdf Nov 2013], [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014jan15_v1.pdf Dec 2013],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/03/jlab_sbs_monthly-report_2014feb15-rmp.pdf Jan 2014], [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014mar15.pdf Feb 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014apr15.pdf Mar 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014may15.pdf Apr 2014]
**Technical Detector Reports
+
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014june15.pdf May 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/07/jlab_sbs_monthly-report_2014july15.pdf June 2014],[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/jlab_sbs_monthly-report_2014aug15-with_gemreport.pdf July 2014]
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/cdet_review_report-final-v1.pdf Super BigBite Coordinate Detector (CDet) Review] by B. Sawatzky, S. Stepanyan, C. Zorn. [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/responsetocdetreviewreport_mk.pdf Response to the Coordinate Detector Review Report] by M. Jones, M. Khandaker, L. Pentchev, A. Sarty, and B. Wojtsekhowski  
+
===Technical Detector Reports===
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/cdet_v3.pdf The concept and main characteristics of the PMT-based Coordinate Detector] by L. Pentchev and B. Wojtsekhowski.
+
====Coordinate Detector====
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/sbs_report2-pre-rd.pdf SBS Gas Electron Multiplier (GEM) Chamber pre-R&D Report] by University of Virginia.
+
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/cdet_review_report-final-v1.pdf Super BigBite Coordinate Detector (CDet) Review] by B. Sawatzky, S. Stepanyan, C. Zorn. [https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/responsetocdetreviewreport_mk.pdf Response to the Coordinate Detector Review Report] by M. Jones, M. Khandaker, L. Pentchev, A. Sarty, and B. Wojtsekhowski  
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/protype_apv25_srs_readout_system.pdf Prototype APV-­‐25 readout system for the SBS back GEM tracker] by University of Virginia.
+
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/cdet_v3.pdf The concept and main characteristics of the PMT-based Coordinate Detector] by L. Pentchev and B. Wojtsekhowski.
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/apv25_readout_system_for_sbs_07_2014.pdf Comparison report of GEM readout systems] by University of Virginia.
+
====Front and Rear GEM trackers====
***[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/italian-daq-report-june23-2014_-v2.pdf APV-25 based readout electronics for the SBS front GEM tracker by INFN]
+
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/sbs_report2-pre-rd.pdf SBS Gas Electron Multiplier (GEM) Chamber pre-R&D Report] by University of Virginia.
 +
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/protype_apv25_srs_readout_system.pdf Prototype APV-­‐25 readout system for the SBS back GEM tracker] by University of Virginia.
 +
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/apv25_readout_system_for_sbs_07_2014.pdf Comparison report of GEM readout systems] by University of Virginia.
 +
*[https://cnidlamp.jlab.org/SBS-experiments/JDocDB/system/files/biblio/2014/08/italian-daq-report-june23-2014_-v2.pdf APV-25 based readout electronics for the SBS front GEM tracker by INFN]

Revision as of 12:28, 23 August 2014

Documentation for Reviewers

Response to DOE 2013 review report

  • Final report from DOE Nov 2013 SBS review.
  • DOE Nov 2013 recommendations with responses.
  1. Update the work flow for GEM module construction to include workforce (by type) required for each step.
    • DOE SBS Nov 2013 monthly report included the work flow for GEM module construction to include workforce (by type).
    • Need Evaristo and Nilanga to update.
  2. Develop a written Quality Assurance/test plan, including acceptance criteria for foils and assembled chambers that will be used for both UVa and INFN.
    • Need Evaristo and Nilanga to create.
  3. Conduct a background assessment for each experimental program that includes background rejection and signal efficiency as a function of trigger cuts, and present at the next review.
    • Seamus is leading the effort.
  4. Develop a document describing the interface between the DAQ system and each of the 3 types of electronics (FADC, GEM, and FASTBUS) and present at the next review.
    • Alexandre is leading the effort.
  5. Integration milestones for all equipment off-project, as well as key JLAB readiness and safety reviews, should be incorporated into the list of milestones. Provide updated list of milestones to DOE by January 1, 2014.
    • List of milestones for off-project equipment dependencies was sent to DOE in Nov 2013 monthly report.
  6. Develop a Technical Specifications Document for all experimental components in the SBS program and present it at the next annual review.
    • Need from each set of equipment a list of technical specs.
  7. Develop an integration plan for all experimental components (on and off project) needed for the SBS program, which includes activities, schedules and goals.
    • Need from each set of equipment a list of activities, schedules and goals.
  8. Update the Research Management Plan to capture current plans for scientific effort needed to implement the project.
    • Research Management Plan. Updated and sent to DOE in Jan 2014 Monthly report.
    • Need one-page activity report from each group to be sent to Brian Quinn
  9. The Project Management Plan should be updated to reflect changes in scope to the WBS components and evolving list of off-project equipment.
    • Program Management Plan. Updated to include PMT based Coordinate Detector and list of off-project equipment dependencies and submitted to DOE in Jan 2014.

DOE SBS Monthly reports

Technical Detector Reports

Coordinate Detector

Front and Rear GEM trackers