Difference between revisions of "Mar 20, 2018"

From Hall A Wiki
Jump to: navigation, search
Line 1: Line 1:
 
Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.php/Weekly_GMn_GEM_commissioning_meeting_at_9am_on_Tuesday Weekly GMn GEM Commissioning Meeting]
 
Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.php/Weekly_GMn_GEM_commissioning_meeting_at_9am_on_Tuesday Weekly GMn GEM Commissioning Meeting]
 
----
 
----
<pre>Kondo, Evaristo, Roberto, Siyu, Bogdan, Nilanga, Leo</pre>
+
<pre>Bogdan, Evaristo, Kondo, Leo, Nilanga, Roberto, Siyu</pre>
  
=== Status of the INFN GEM Cosmic Stand (Roberto) ===
+
=== Status of the INFN GEM Cosmic Stand ===
  
 
*Provide the FNAL Test beam update.
 
*Provide the FNAL Test beam update.

Revision as of 11:26, 20 March 2018

Link to all previous meetings: Weekly GMn GEM Commissioning Meeting


Bogdan, Evaristo, Kondo, Leo, Nilanga, Roberto, Siyu

Status of the INFN GEM Cosmic Stand

  • Provide the FNAL Test beam update.
  • They completed a scan of the multi-ZZ pattern PCB, along with gain and gap field scans.
  • Have other ZZ boards we want to test as well, including micromegas based detectors with ZZ readout.
  • Overall things are going well. They will report more in two weeks.

Status of the UVa GEM Cosmic Stand

  • They receive the new longer screws, will prepare them (cleaning etc ...) for assembly.
  • Will put the mock chamber together once more this week to check if gas leak issue is fixed with the longer screws

AOB