Difference between revisions of "May 6, 2018"
(Created page with "Back to Main Page >> Moller Page >> Moller Weekly Meeting Index previous meeting << >> May_13%2C_2...") |
|||
Line 13: | Line 13: | ||
Agenda: | Agenda: | ||
*Onsite update -- Simona/Roman/Sanghwa | *Onsite update -- Simona/Roman/Sanghwa | ||
− | *Simulation update -- Eric | + | *Simulation update -- Eric [https://hallaweb.jlab.org/dvcslog/moller/102 here] |
− | + | ||
---- | ---- | ||
Line 34: | Line 34: | ||
Minutes | Minutes | ||
---- | ---- | ||
+ | Simona could not make it but sent an email update which is reproduced here. | ||
+ | |||
+ | Hi Guys, | ||
+ | I won't be able to participate in the meeting today (Hall work) but here is a Moller update: | ||
+ | |||
+ | --> the target motion system is ready (Ethan got the pieces from the machine shop last week and did the installation); he still needs to test the motion to make sure everything is working O.K. | ||
+ | |||
+ | --> Dave Meekins got even busier with other things and did not attempt to install the Copper foil yet but there is time; he is aware of the deadline and he will make it (I asked the survey group to do the target survey anytime after May 20th) | ||
+ | |||
+ | |||
+ | --> Yves got back to me about running 1 muA on the 4 micron target without too many ion chambers trips: he said it's not a problem; with new ion chambers calibrations and also a procedure of "how to do things efficiently" which they wrote down since commissionning it will work. | ||
+ | |||
+ | |||
+ | --> Today the scintillator PMTs have been delivered to my office. I will do a dark box test next week and I will install them in the detector shortly after. | ||
+ | |||
+ | |||
+ | --> next week I will also work on getting the 4 BPM signals into the scaler module. | ||
+ | |||
+ | |||
+ | In two weeks from now I will give another DAQ update (including the TDC readout). | ||
+ | |||
+ | |||
+ | That's all I have for this week. | ||
+ | |||
+ | |||
+ | Have a good week, | ||
+ | |||
+ | |||
+ | Simona |
Revision as of 14:42, 6 May 2019
Back to Main Page >> Moller Page >> Moller Weekly Meeting Index
previous meeting << >> following meeting
Original Moller Polarimeter Page
Agenda:
- Onsite update -- Simona/Roman/Sanghwa
- Simulation update -- Eric here
Connection details:
Meeting URL https://bluejeans.com/388466836
Meeting ID 388 466 836
US toll free phone 1.888.240.2560
Dial in, type in the meeting ID and then press ##
Minutes
Simona could not make it but sent an email update which is reproduced here.
Hi Guys, I won't be able to participate in the meeting today (Hall work) but here is a Moller update:
--> the target motion system is ready (Ethan got the pieces from the machine shop last week and did the installation); he still needs to test the motion to make sure everything is working O.K.
--> Dave Meekins got even busier with other things and did not attempt to install the Copper foil yet but there is time; he is aware of the deadline and he will make it (I asked the survey group to do the target survey anytime after May 20th)
--> Yves got back to me about running 1 muA on the 4 micron target without too many ion chambers trips: he said it's not a problem; with new ion chambers calibrations and also a procedure of "how to do things efficiently" which they wrote down since commissionning it will work.
--> Today the scintillator PMTs have been delivered to my office. I will do a dark box test next week and I will install them in the detector shortly after.
--> next week I will also work on getting the 4 BPM signals into the scaler module.
In two weeks from now I will give another DAQ update (including the TDC readout).
That's all I have for this week.
Have a good week,
Simona