Difference between revisions of "SoLID Weekly : Monday, May.20, 2019 9:30am EDT"

From Hall A Wiki
Jump to: navigation, search
(Minutes)
(Minutes)
Line 12: Line 12:
 
*Thia: What's the timeline for the estimation?  
 
*Thia: What's the timeline for the estimation?  
 
*JP: We try to put everything together this week.  
 
*JP: We try to put everything together this week.  
*
+
*JP:The subsystem of SoLID is independent, so you can buy and certain things in the subsystem individually.
  
 
==Present==
 
==Present==
 
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen
 
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen

Revision as of 09:49, 20 May 2019

Agenda

  • Discussion on SoLID cost estimation according to WBS (Work Breakdown

Structure)

  • Sub-system updates

Minutes

  • JP: Thia, Do you want to give a summary
  • Thia: I received LGC cost estimation. I think at this the point, the break down level makes sense for me, everything looks pretty good. However for a 5-year duration project, maybe it is worth to put the installation in the estimation.
  • Alexandre: Does this 5-year duration include 2-year preR&D and 3-year project?
  • JP: preR&D is not included in this duration.
  • JP: If the sub-system hasn't sent me the revised version, please sent it to me as soon as possible.
  • Thia: What's the timeline for the estimation?
  • JP: We try to put everything together this week.
  • JP:The subsystem of SoLID is independent, so you can buy and certain things in the subsystem individually.