Difference between revisions of "2009 Holiday Schedule"
From Hall A Wiki
(→Survey with the old needle horizontal compass) |
(→Dec 22, Monday, 2008) |
||
Line 1: | Line 1: | ||
== Dec 22, Monday, 2008 == | == Dec 22, Monday, 2008 == | ||
− | # | + | # AFP loss test of vertical pumping (HRS on) |
− | # | + | # EPR of vertical pumping (HRS on) |
− | # HRS | + | # NMR of vertical pumipng (HRS on) |
− | # Check laser spectrum with cell | + | # Vertical temperature test @ pickup coil position (HRS on) |
+ | # lunch and pumping | ||
+ | # Vertical HRS test | ||
+ | # Longitudinal HRS test | ||
+ | # Chiranjib's temperature test | ||
+ | # Check laser spectrum with cell ? | ||
# Cool down oven | # Cool down oven | ||
Revision as of 11:27, 22 December 2008
Contents
Dec 22, Monday, 2008
- AFP loss test of vertical pumping (HRS on)
- EPR of vertical pumping (HRS on)
- NMR of vertical pumipng (HRS on)
- Vertical temperature test @ pickup coil position (HRS on)
- lunch and pumping
- Vertical HRS test
- Longitudinal HRS test
- Chiranjib's temperature test
- Check laser spectrum with cell ?
- Cool down oven
Dec 23, Tuesday, 2008
- RadCon surveys the target enclosure
- remove the 3He cell and target ladder
- Install water cell
- Prepare for water calibration: require turning off pump, other environment noise.
- Water calibration
Dec 24, Wednesday, 2008
- Water calibration
Dec 25, Thursday, 2008 - Jan 4, Sunday, 2009
- Compass measurement: Transverse, Vertical (optional)
Jan 5, Monday, 2009
Survey with the new horizontal compass
- With Transverse- field, put the new Horizontal Compass at Center point and align the laser before Survey starts
- Survey the first point: Transverse- Center
- Move compass to Upstream, align the laser (~ 30min)
- Survey the second point: Transverse- Upstream
- Move compass to Downstream, align the laser (~ 30min)
- Survey the third point: Transverse- Downstream
Survey with the old needle horizontal compass
- Keeping Transverse- field, put the old needle horizontal compass at the center point (~ 5min)
- Survey the fourth point: Transverse-
- Change the field to Transverse+ (~ 5min)
- Survey the fifth point: Transverse+
- Change the field to Longitudinal+ (~ 5min)
- Survey the sixth point: Longitudinal+
- Change the field to Longitudinal- (~ 5min)
- Survey the seventh point: Longitudinal-
After compass survey
- Install 3He cell and ladder
Jan 6, Tuesday, 2009
- Target Survey
Jan 7, Wednesday, 2009 - Beam start
- Laser check
- Pumping
- Polarization calibration