From Hall A Wiki
Line 1: | Line 1: | ||
*Updates | *Updates | ||
**HCal | **HCal | ||
+ | ***Cables from FE to bunker : about 20% done ~ 2weeks to complete - could use man power to unroll cable while 2 people installing | ||
+ | ***5 to 9 Sebastian and Provokar out of town | ||
+ | ***power to HCAL racks - still no power - issue with transformer - Jack thinks transformer might not have enough power | ||
**Bigbite Shower | **Bigbite Shower | ||
+ | ***starting laying cable | ||
+ | ***HV cables were found to be to short ( 25 m - need 30 m) - 10 m extension found - making more extensions - signals cables not laid out | ||
+ | ***HV location changed | ||
+ | ***BB shower VXS | ||
**Bigbite Hodoscope | **Bigbite Hodoscope | ||
+ | ***working in Hall staging cables : ADC cables in bunker ready to be plug when BB cable tray is installed, waiting for cable tray for detector to bunker | ||
+ | ***Rachel and David working on SBS-Offline software | ||
**GRINCH | **GRINCH | ||
+ | ***Fully cabled : ADC and TDC at both ends, some slack left in middle way, can adjust if needed | ||
+ | ***ADC cables on detector | ||
+ | ***just need HV to take data | ||
+ | ***LV cable needs to be extended for NINO supply | ||
+ | ***some cables connectors need to be repaired | ||
+ | ***will setup GRINCH CODA on counting house computer | ||
+ | ***repeater rack is in bunker - 100 m TDC cables | ||
**LHRS | **LHRS | ||
+ | ***Maria plots of A1 | ||
+ | ***VDC maybe one bad card : Jack knows about it | ||
+ | ***Scaler server from Steve setup for both crates | ||
+ | ***Scaler ordered postponed to Oct 1 | ||
**CDet | **CDet | ||
+ | ***taking data, fixing problems | ||
+ | ***identified replacement PMTs | ||
+ | ***HV still running | ||
**GEM BB Hall A | **GEM BB Hall A | ||
+ | ***fibers setup | ||
+ | ***LV ready | ||
+ | ***can power up on Monday | ||
+ | ***Bryan get closer to completion, Ben showed ROC part working for FADC | ||
+ | ***ready next week for VTP in Hall A if needed | ||
**GEM INFN Test Lab | **GEM INFN Test Lab | ||
+ | ***Test SSP readout | ||
**GEM UVA | **GEM UVA | ||
+ | ***working on shielding | ||
**Beamline | **Beamline | ||
+ | ***software, monitoring scripts almost setup, writing shifter documentation | ||
+ | ***looking at PREX alarm handler | ||
**Helicity | **Helicity | ||
+ | ***Bob and Paul, will go in LHRS to install scalers - One scaler has a bad user bit 2 and on has a broken NIM input - could use ECL - ECL scaler - could use one scaler from scaler crate at entrance of hall | ||
+ | ***work on analysis software TQWeak class compatible and should be | ||
**HV | **HV | ||
**Scalers | **Scalers | ||
+ | ***2eVME | ||
+ | ***Crate to be installed under hodoscope | ||
+ | *VME controllers | ||
+ | **Bryan helping set up, most should be up in a few days | ||
+ | |||
Line 20: | Line 59: | ||
**3 rd GEM VXS crate install router moved up ( 75% ) | **3 rd GEM VXS crate install router moved up ( 75% ) | ||
**need power and network in GEM bunker | **need power and network in GEM bunker | ||
− | **detector accounts setup | + | **detector accounts setup ( check with Ole ) |
**boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers) | **boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers) | ||
− | **detector cabling | + | **detector cabling - |
**new MPD production - about to start - need to ship our FPGA to Paolo | **new MPD production - about to start - need to ship our FPGA to Paolo | ||
**MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot | **MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot | ||
+ | **setup portservers | ||
+ | **need to install remote switch for crate in bunker - rest are VXS or VME64 | ||
**Bigbite - HCal trigger setup | **Bigbite - HCal trigger setup | ||
**TS setup - 0% | **TS setup - 0% | ||
Line 33: | Line 74: | ||
**Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne | **Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne | ||
**LHRS fiber pull | **LHRS fiber pull | ||
+ | |||
+ | |||
*Outstanding issues | *Outstanding issues | ||
− | **2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC | + | **2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC |
**SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) | **SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) | ||
**need to adjust for HCAL transit time with different PMTs | **need to adjust for HCAL transit time with different PMTs | ||
− | **status of cosmics paddles | + | **status of cosmics paddles ( installed by Bogdan ) |
**GEM fibers too short : 60 m ordered | **GEM fibers too short : 60 m ordered | ||
**15 bad MPDs | **15 bad MPDs |
Latest revision as of 11:27, 30 July 2021
- Updates
- HCal
- Cables from FE to bunker : about 20% done ~ 2weeks to complete - could use man power to unroll cable while 2 people installing
- 5 to 9 Sebastian and Provokar out of town
- power to HCAL racks - still no power - issue with transformer - Jack thinks transformer might not have enough power
- Bigbite Shower
- starting laying cable
- HV cables were found to be to short ( 25 m - need 30 m) - 10 m extension found - making more extensions - signals cables not laid out
- HV location changed
- BB shower VXS
- Bigbite Hodoscope
- working in Hall staging cables : ADC cables in bunker ready to be plug when BB cable tray is installed, waiting for cable tray for detector to bunker
- Rachel and David working on SBS-Offline software
- GRINCH
- Fully cabled : ADC and TDC at both ends, some slack left in middle way, can adjust if needed
- ADC cables on detector
- just need HV to take data
- LV cable needs to be extended for NINO supply
- some cables connectors need to be repaired
- will setup GRINCH CODA on counting house computer
- repeater rack is in bunker - 100 m TDC cables
- LHRS
- Maria plots of A1
- VDC maybe one bad card : Jack knows about it
- Scaler server from Steve setup for both crates
- Scaler ordered postponed to Oct 1
- CDet
- taking data, fixing problems
- identified replacement PMTs
- HV still running
- GEM BB Hall A
- fibers setup
- LV ready
- can power up on Monday
- Bryan get closer to completion, Ben showed ROC part working for FADC
- ready next week for VTP in Hall A if needed
- GEM INFN Test Lab
- Test SSP readout
- GEM UVA
- working on shielding
- Beamline
- software, monitoring scripts almost setup, writing shifter documentation
- looking at PREX alarm handler
- Helicity
- Bob and Paul, will go in LHRS to install scalers - One scaler has a bad user bit 2 and on has a broken NIM input - could use ECL - ECL scaler - could use one scaler from scaler crate at entrance of hall
- work on analysis software TQWeak class compatible and should be
- HV
- Scalers
- 2eVME
- Crate to be installed under hodoscope
- HCal
- VME controllers
- Bryan helping set up, most should be up in a few days
- On-going tasks
- Network setup ( done )
- Scaler crate setup (75 % - need put crate in / setup cpu )
- 3 rd GEM VXS crate install router moved up ( 75% )
- need power and network in GEM bunker
- detector accounts setup ( check with Ole )
- boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
- detector cabling -
- new MPD production - about to start - need to ship our FPGA to Paolo
- MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
- setup portservers
- need to install remote switch for crate in bunker - rest are VXS or VME64
- Bigbite - HCal trigger setup
- TS setup - 0%
- Beamline crate setup ( in scaler crate )
- HCAL cabling
- HCAL need power
- Mark hodoscope trigger ?
- Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
- LHRS fiber pull
- Outstanding issues
- 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
- SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
- need to adjust for HCAL transit time with different PMTs
- status of cosmics paddles ( installed by Bogdan )
- GEM fibers too short : 60 m ordered
- 15 bad MPDs