On-going tasks
 
Network setup ( done )
 
Scaler crate setup (75 % - need put crate in / setup cpu )
 
3 rd GEM VXS crate install router moved up ( 75% )
 
need power and network in GEM bunker
 
detector accounts setup ( check with Ole )
 
boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
 
detector cabling -
 
new MPD production - about to start - need to ship our FPGA to Paolo
 
MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
 
setup portservers
 
need to install remote switch for crate in bunker - rest are VXS or VME64
 
Bigbite - HCal trigger setup
 
TS setup - 0%
 
Beamline crate setup ( in scaler crate )
 
HCAL cabling
 
HCAL need power
 
Mark hodoscope trigger ?
 
Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
 
LHRS fiber pull
 
  
Outstanding issues
 
2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
 
SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
 
need to adjust for HCAL transit time with different PMTs
 
status of cosmics paddles ( installed by Bogdan )
 
GEM fibers too short : 60 m ordered
 
15 bad MPDs
 