− | On-going tasks
| |
− | Network setup ( done )
| |
− | Scaler crate setup (75 % - need put crate in / setup cpu )
| |
− | 3 rd GEM VXS crate install router moved up ( 75% )
| |
− | need power and network in GEM bunker
| |
− | detector accounts setup ( check with Ole )
| |
− | boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
| |
− | detector cabling -
| |
− | new MPD production - about to start - need to ship our FPGA to Paolo
| |
− | MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
| |
− | setup portservers
| |
− | need to install remote switch for crate in bunker - rest are VXS or VME64
| |
− | Bigbite - HCal trigger setup
| |
− | TS setup - 0%
| |
− | Beamline crate setup ( in scaler crate )
| |
− | HCAL cabling
| |
− | HCAL need power
| |
− | Mark hodoscope trigger ?
| |
− | Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
| |
− | LHRS fiber pull
| |
| | | |
− | Outstanding issues
| |
− | 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
| |
− | SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
| |
− | need to adjust for HCAL transit time with different PMTs
| |
− | status of cosmics paddles ( installed by Bogdan )
| |
− | GEM fibers too short : 60 m ordered
| |
− | 15 bad MPDs
| |