Temperature controller for Hall C Ar/Neon mixer (Joe has started)
 
Temperature controller for Hall C Ar/Neon mixer (Joe has started)
  
Heaters for SHMS magnet flags./ Guard modifications complete, waiting on controller
+
Heaters for SHMS magnet flags./ Guard modifications complete, waiting on controller, fans installed, managing ice well.
  
 
Heaters for HMS magnet flags-Heaters, modifications to guards complete, heaters installed.  Waiting on controller.
 
Heaters for HMS magnet flags-Heaters, modifications to guards complete, heaters installed.  Waiting on controller.
Line 25: Line 25:
 
Ground power supplies and corrector supply racks in DAQ Bunker (not started)
 
Ground power supplies and corrector supply racks in DAQ Bunker (not started)
  
Install magnet leads for SBB (535 MCM cable) (started)
+
Install magnet leads for SBB (535 MCM cable) (cables run, waiting on copper bus bars) (connections still need to be torqued)  
  
Install magnet leads for SBB corrector magnets (2 AWG welding cable) (cable is in hand)
+
Install magnet leads for SBB corrector magnets (2 AWG welding cable) (cables run, Reagan is making final connections, only three power supplies in rack)
  
Connect SBB and corrector magnets to FSD (ADC is installed)
+
Connect SBB and corrector magnets to FSD (ADC is installed)(cables run/landed and verified, ch1 upstream left, ch2 upstream right, ch3 downstream left, ch4 downstream right, ch5 SBS)
  
 
Ground HCAL, racks, and support frame (started)
 
Ground HCAL, racks, and support frame (started)
Line 48: Line 48:
  
 
Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (mostly done)
 
Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (mostly done)
 +
 +
Install thermistors on SBS/Big Bite magnets and junction boxes.
 +
 +
Install Kilxons on SBS?
 +
 +
Install Klixons on Big Bite?
  
  

Revision as of 09:24, 27 August 2021

Priority Items

Hall A Moller Polarimeter target magnet re-install: helium recharge, compressor and chiller clean up and setup, testing (pumping down on cold head)

Temperature controller for Hall C Ar/Neon mixer (Joe has started)

Heaters for SHMS magnet flags./ Guard modifications complete, waiting on controller, fans installed, managing ice well.

Heaters for HMS magnet flags-Heaters, modifications to guards complete, heaters installed. Waiting on controller.

Install S0 counter above BB for a cosmics trigger.

Locking bar for the Right Shield House (have bar - needs two holes drilled)

Roofing material for SBS GEM bunker (located some possible material - will run past Jessie)

Jumper bars for SBB coils (looking for 4" x 1/2" bars to buy)

Controls for SBB and corrector coils (waiting for power to the supplies)

Re-tap the SBB supply main transformer for full power (Joe will start after renewing his training)

Connect 480VAC for SBB and corrector power supplies (waiting on the electricians)(need to block up the correctors' racks)

Ground power supplies and corrector supply racks in DAQ Bunker (not started)

Install magnet leads for SBB (535 MCM cable) (cables run, waiting on copper bus bars) (connections still need to be torqued)

Install magnet leads for SBB corrector magnets (2 AWG welding cable) (cables run, Reagan is making final connections, only three power supplies in rack)

Connect SBB and corrector magnets to FSD (ADC is installed)(cables run/landed and verified, ch1 upstream left, ch2 upstream right, ch3 downstream left, ch4 downstream right, ch5 SBS)

Ground HCAL, racks, and support frame (started)

re-install ground fault detector in LQ1 supply - requires configuration of module (not started)

connect power and LCW to BB supply on R-arm platform (not started)

Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (need Steven).

Gas manifolds for GEM gas cylinders (started)

Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)

Gas mix controller and MFCs for GEM detectors (not started)

Readout for LCW pressure sensors added at end of beamline walkway (not started)

Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (mostly done)

Install thermistors on SBS/Big Bite magnets and junction boxes.

Install Kilxons on SBS?

Install Klixons on Big Bite?


Would Be Good To Do Items

Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker

Remove actuators from right arm magnets. (Dipole complete)

clean up R-arm supply platform

clean up L-arm supply platform

Swap out MFCs in VDC mixing system

Remove three Oxford power supplies from HMS


Possible Future Items

Replace air compressor in Hall A Gas Shed (on hold till next fiscal year)