<s>Install thermistors on SBS/Big Bite magnets and junction boxes.</s> Done.
 
<s>Install thermistors on SBS/Big Bite magnets and junction boxes.</s> Done.
  
Install Klixons on SBB.</s> Done.
+
<s>Install Klixons on SBB.</s> Done.
  
 
Mount Left Shield House temperature readout in CH
 
Mount Left Shield House temperature readout in CH

Revision as of 15:30, 4 October 2021

Priority Items

Jumper bars for SBB coils (Done)

Controls for SBB and corrector coils (waiting for water to the magnets, software updates)

Install magnet leads for SBB (535 MCM cable) (done)

Connect magnet leads for SBB corrector magnets (done)

Readout for LCW pressure sensors added at end of beamline walkway (not started)

Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (Done, BB and SBS need tested, correctors work)

Install thermistors on SBS/Big Bite magnets and junction boxes. Done.

Install Klixons on SBB. Done.

Mount Left Shield House temperature readout in CH

Find video cables from hall in the CH

Measure current on 12V supplies in HMS magnet supplies when hall C is open long enough

Would Be Good To Do Items

Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker

Test LQ2 FuG with new polarity reversal switch.

Find and connect NMR cables in CH

Gas manifolds for GEM gas cylinders (started)

Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)

Gas mix controller and MFCs for GEM detectors (not started)

Roofing material for SBS GEM bunker (located some possible material - will run past Jessie)

Remove actuators from right arm magnets. (Dipole complete)

clean up R-arm supply platform

clean up L-arm supply platform

Swap out MFCs in VDC mixing system

HMS/SHMS Heater and fan changes, fixes, upgrades etc.

PARTS ORDER LIST FOR 1 OCT

-2 wire cable, ferrules, \# 6 hardware

Possible Future Items

Replace air compressor in Hall A Gas Shed (on hold till next fiscal year)

Remote reset for Hall C spectrometer motion (maybe next year)

Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (need Steven).