Difference between revisions of "Meeting 2021 11 24"

From Hall A Wiki
Jump to: navigation, search
(Update on INFN GEM layers for GEn-RP (Ezekiel))
Line 11: Line 11:
 
* Resistor added to BB UV layer 2 on Wednesday.
 
* Resistor added to BB UV layer 2 on Wednesday.
 
* Plan to take HV scan on all three UV layers in BB. See [https://docs.google.com/spreadsheets/d/19jD5AEY7XemTJ8pL2gt7NlVbc49LKnNyNfLFP7bC6Lk/edit?usp=sharing spreadsheet]
 
* Plan to take HV scan on all three UV layers in BB. See [https://docs.google.com/spreadsheets/d/19jD5AEY7XemTJ8pL2gt7NlVbc49LKnNyNfLFP7bC6Lk/edit?usp=sharing spreadsheet]
 +
* Anu will start working as the GEM expert on call for this week starting today evening.
  
 
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) ===
 
=== Update on UVa GEM layers for GEn-RP (Anu, John, Thir) ===
*
+
* Working on the GEM database for tracking analysis on GEn-RP cosmic setup in EEL/125 which will eventually be extended to for Hall setup. Yesterday we had a productive meeting with Andrew where he helped us to get things started. Will continue to work with him continuously until we are able to use his scripts for tracking.
  
 
=== Update on INFN GEM layers for GEn-RP (Ezekiel) ===
 
=== Update on INFN GEM layers for GEn-RP (Ezekiel) ===

Revision as of 10:09, 24 November 2021

GMn GEM commissioning Meetings: WEDNESDAY 10:00am - 11:00am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Update on BB GEMs(Sean, Ezekiel, Holly, Anu)

  • GEM layer was swapped last Wednesday.
  • Two APVs fixed on the GEM layer on Thursday.
  • Resistor added to BB UV layer 2 on Wednesday.
  • Plan to take HV scan on all three UV layers in BB. See spreadsheet
  • Anu will start working as the GEM expert on call for this week starting today evening.

Update on UVa GEM layers for GEn-RP (Anu, John, Thir)

  • Working on the GEM database for tracking analysis on GEn-RP cosmic setup in EEL/125 which will eventually be extended to for Hall setup. Yesterday we had a productive meeting with Andrew where he helped us to get things started. Will continue to work with him continuously until we are able to use his scripts for tracking.

Update on INFN GEM layers for GEn-RP (Ezekiel)

  • Resolving HV trouble on J1 top (seems due to shielding). APVs that are not well connected (id from cosmics) were repaired.
  • Plan to take a longer HV run for the whole layer this week.
  • Will need to repair a few APVs on J3.

Update on the Tracking efficiency / resolution (Andrew)

Update on the High rate DAQ development (Ben, Bryan, Alex, Holly)